Normal Bench Digging versus Bench Chopping of a Dragline Excavator in Terms of Cycle Times, Cycle Time Components and Energy Consumption Parameters - A Case Study

Year 2010, Volume: 49 Issue: 3, 31 - 37, 01.09.2010

Abstract

In this article, dragline normal bench digging and bench chopping are explained in general and the
results of studies with both types of digging are given for a 15 m3 bucket P&H/Page 736 model dragline
excavator in terms of cycle time, components, and energy consumption. Measurements were made
from the control panel of the equipment by recording the cycle times and the armature voltage and
feedback current signals for drag, hoist and swing direct current motors. Measuring system and the
principle of calculation of DC motor power and energy are given. 74 bench chopping cycles and 59
normal bench digging cycles were monitored at two adjacent dragline slices (benches). Monitored
parameters of both digging modes are given and compared. Bench chopping is discussed in terms of
productivity, bucket fill factor, impact on bucket and rigging. Furthermore,components comprising work
cycle in terms of time and energy consumption are investigated and interpreted. The reason for the
comparetively lower energy consumption in swing motion is explained.

ÇEKME KEPÇELİ YERKAZARDA OLAĞAN BASAMAK KAZISI İLE TEPEDEN KAZIDA İŞ DÖNGÜ SÜRELERİ, BİLEŞENLERİ VE ENERJİ TÜKETİM DEĞİŞKENLERİ KARŞILAŞTIRMASI - OLAY ÇALIŞMASI

Year 2010, Volume: 49 Issue: 3, 31 - 37, 01.09.2010

Abstract

Bu yazıda çekme kepçe olağan basamak kazısı ile tepeden kazı hakkında genel bilgi verilmiş olup 15
m3 kapasiteli bir P&H/Page 736 model yerkazarda, her iki tür kazıda yapılan iş döngü süresi, bileşenleri
ve enerji tüketim ölçüm ve sonuçları verilmiştir. Ölçümler kontrol panelinde çektiriş, kaldırış, döndürüş
doğru akım motorları için mevcut test sinyal çıkış noktalarından, armatür voltaj ve akım geri besleme
sinyalleri ve çalışma döngüsü süreleri kaydedilerek yapılmıştır. Ölçüm sistemi ve DC motor güç ve
enerji hesaplama ilkesine kısaca değinilmiştir. Bitişik iki çekme kepçe diliminde (basamak) ölçülen 59
adet normal basamak kazısı ve 74 adet tepeden kazı iş döngüsü süre ve enerji yönünden incelenmiştir.
Her iki tür kazıda izlenen değişkenler verilmiş ve birbiri ile karşılaştırılmıştır. Tepeden kazı yöntemi;
üretkenlik, kova dolma çarpanı, kova ve donanımına etkileri yönünden tartışılmıştır. Ayrıca, iş döngüsü
bileşenleri süre ve enerji tüketimi yönünden incelenip yorumlanmıştır. Döndürüş deviniminin düşük
enerji tüketimi nedeni açıklanmıştır.

There are 0 citations in total.

Details

Other ID JA92DT77NN
Journal Section Technical Notes
Authors

Metin Özdoğan This is me

Abdurrahim Özgenoğlu This is me

Publication Date September 1, 2010
Submission Date September 1, 2010
Published in Issue Year 2010 Volume: 49 Issue: 3

Cite

APA Özdoğan, M., & Özgenoğlu, A. (2010). ÇEKME KEPÇELİ YERKAZARDA OLAĞAN BASAMAK KAZISI İLE TEPEDEN KAZIDA İŞ DÖNGÜ SÜRELERİ, BİLEŞENLERİ VE ENERJİ TÜKETİM DEĞİŞKENLERİ KARŞILAŞTIRMASI - OLAY ÇALIŞMASI. Bilimsel Madencilik Dergisi, 49(3), 31-37.
AMA Özdoğan M, Özgenoğlu A. ÇEKME KEPÇELİ YERKAZARDA OLAĞAN BASAMAK KAZISI İLE TEPEDEN KAZIDA İŞ DÖNGÜ SÜRELERİ, BİLEŞENLERİ VE ENERJİ TÜKETİM DEĞİŞKENLERİ KARŞILAŞTIRMASI - OLAY ÇALIŞMASI. Mining. September 2010;49(3):31-37.
Chicago Özdoğan, Metin, and Abdurrahim Özgenoğlu. “ÇEKME KEPÇELİ YERKAZARDA OLAĞAN BASAMAK KAZISI İLE TEPEDEN KAZIDA İŞ DÖNGÜ SÜRELERİ, BİLEŞENLERİ VE ENERJİ TÜKETİM DEĞİŞKENLERİ KARŞILAŞTIRMASI - OLAY ÇALIŞMASI”. Bilimsel Madencilik Dergisi 49, no. 3 (September 2010): 31-37.
EndNote Özdoğan M, Özgenoğlu A (September 1, 2010) ÇEKME KEPÇELİ YERKAZARDA OLAĞAN BASAMAK KAZISI İLE TEPEDEN KAZIDA İŞ DÖNGÜ SÜRELERİ, BİLEŞENLERİ VE ENERJİ TÜKETİM DEĞİŞKENLERİ KARŞILAŞTIRMASI - OLAY ÇALIŞMASI. Bilimsel Madencilik Dergisi 49 3 31–37.
IEEE M. Özdoğan and A. Özgenoğlu, “ÇEKME KEPÇELİ YERKAZARDA OLAĞAN BASAMAK KAZISI İLE TEPEDEN KAZIDA İŞ DÖNGÜ SÜRELERİ, BİLEŞENLERİ VE ENERJİ TÜKETİM DEĞİŞKENLERİ KARŞILAŞTIRMASI - OLAY ÇALIŞMASI”, Mining, vol. 49, no. 3, pp. 31–37, 2010.
ISNAD Özdoğan, Metin - Özgenoğlu, Abdurrahim. “ÇEKME KEPÇELİ YERKAZARDA OLAĞAN BASAMAK KAZISI İLE TEPEDEN KAZIDA İŞ DÖNGÜ SÜRELERİ, BİLEŞENLERİ VE ENERJİ TÜKETİM DEĞİŞKENLERİ KARŞILAŞTIRMASI - OLAY ÇALIŞMASI”. Bilimsel Madencilik Dergisi 49/3 (September 2010), 31-37.
JAMA Özdoğan M, Özgenoğlu A. ÇEKME KEPÇELİ YERKAZARDA OLAĞAN BASAMAK KAZISI İLE TEPEDEN KAZIDA İŞ DÖNGÜ SÜRELERİ, BİLEŞENLERİ VE ENERJİ TÜKETİM DEĞİŞKENLERİ KARŞILAŞTIRMASI - OLAY ÇALIŞMASI. Mining. 2010;49:31–37.
MLA Özdoğan, Metin and Abdurrahim Özgenoğlu. “ÇEKME KEPÇELİ YERKAZARDA OLAĞAN BASAMAK KAZISI İLE TEPEDEN KAZIDA İŞ DÖNGÜ SÜRELERİ, BİLEŞENLERİ VE ENERJİ TÜKETİM DEĞİŞKENLERİ KARŞILAŞTIRMASI - OLAY ÇALIŞMASI”. Bilimsel Madencilik Dergisi, vol. 49, no. 3, 2010, pp. 31-37.
Vancouver Özdoğan M, Özgenoğlu A. ÇEKME KEPÇELİ YERKAZARDA OLAĞAN BASAMAK KAZISI İLE TEPEDEN KAZIDA İŞ DÖNGÜ SÜRELERİ, BİLEŞENLERİ VE ENERJİ TÜKETİM DEĞİŞKENLERİ KARŞILAŞTIRMASI - OLAY ÇALIŞMASI. Mining. 2010;49(3):31-7.

22562 22561 22560 22590 22558