PROJECT PLANNING WITH CPM AND PERT METHODS: EXAMPLE OF DEFENCE INDUSTRY
Abstract
Project management is the process of planning activities in the project, estimating time and cost, assigning resources, making schedules, and performing controls. Project planning methods are used in project management to make time estimations. CPM, PERT, Gantt Charts, Fuzzy CPM, Fuzzy PERT are project planning methods. The CPM method is used when the activity durations are known certainly. However, in a project implemented for the first time, the duration of activity cannot be estimated certainly. In order to take this variability into account, the PERT method, which calculates the optimistic, probable and pessimistic durations of the activities, is used. Defense industry projects are of great importance as they are related to the defense of the country. In order for defense industry projects to be successful, the projects must be planned effectively. In this study, the planning process of a project realized for the first time by a company serving in the defense industry was examined. In the study, first of all, the activities of the project, their previous activites and duration are defined. In the study, the completion time of the project was calculated using CPM and PERT methods and the results were compared. In the last part of the study, the completion time of the project was calculated under different probabilities by using the PERT method.
Keywords
References
- Abdel-Basset, M., Atef, A., Abouhawwash, M., Nam, Y., and AbdelAziz, M.N. (2022) “Network analysis for projects with high risk levels in uncertain environments”, Computers, Materials & Continua, Vol. 70 Issue 1, pp. 1281-1296. doi: 10.32604/cmc.2022.018947.
- Agyei, W. (2015). “Project planning and scheduling using PERT and CPM techniques with linear programming: case study”, International journal of scientific & technology research, Vol. 4 Issue 8, pp. 222-227.
- Aksoy, A., Akansel, M., Atalay, C., Çamlıbel, A. M., Yaşar, D., Keseroğlu, D., and Vanlıoğlu, S. (2019). “Proje Yönetiminde Zaman ve Maliyet Odaklı Bütünleşik Planlama Yaklaşımı ve Bir Uygulama”, Journal of Entrepreneurship and Innovation Management, Vol. 8 Issue 1, pp. 1-20.
- Anderson, D.R., Sweeney, D.J., Williams, T.A., Camm, J.D., and Cochran, J.J. (2012). Quantitative Methods for Business. Cengage Learning, Hampshire.
- Çetmeli, E. (1982). Yatırım planlamasında kritik yörünge ve PERT metodları, Teknik Kitaplar Yayınevi, İstanbul. Gašparíková, Z., and Leitner, B. (2021). “Application of the PERT method in planning of area evacuation of persons”, Transportation research procedia, Vol. 55, pp. 1547-1554. doi: 10.1016/j.trpro.2021.07.144.
- Gül, M., Güneri, A. F., and Güneş, G. (2017). “Project management in healthcare: A case study for patient flow evaluation in an emergency room using fuzzy CPM and fuzzy PERT”, Sigma, Vol. 8 Issue 1, pp. 41-51.
- Gencer, C., and Türkbey, O. (2001). “Proje Tamamlanma Zamanının Bulunmasında İstatistiksel Analiz Yardımıyla Bulanık-PERT, Klasik-PERT ve Gerçek-Dağılım Yöntemlerinin Karşılaştırılması”, Dokuz Eylül Üniversitesi Mühendislik Fakültesi Fen ve Mühendislik Dergisi, Vol. 3, Issue 2, pp. 29-39.
- Kelly, J.E., and Walker, M.R. (1957). The Critical Path Method. Remington Rand and DuPont Corporation.
Details
Primary Language
English
Subjects
Engineering
Journal Section
Research Article
Authors
Publication Date
November 30, 2022
Submission Date
April 13, 2022
Acceptance Date
May 16, 2022
Published in Issue
Year 2022 Volume: 18 Number: 2
APA
Desticioğlu, B. (2022). PROJECT PLANNING WITH CPM AND PERT METHODS: EXAMPLE OF DEFENCE INDUSTRY. Journal of Naval Sciences and Engineering, 18(2), 363-385. https://izlik.org/JA97WD85CF
AMA
1.Desticioğlu B. PROJECT PLANNING WITH CPM AND PERT METHODS: EXAMPLE OF DEFENCE INDUSTRY. JNSE. 2022;18(2):363-385. https://izlik.org/JA97WD85CF
Chicago
Desticioğlu, Beste. 2022. “PROJECT PLANNING WITH CPM AND PERT METHODS: EXAMPLE OF DEFENCE INDUSTRY”. Journal of Naval Sciences and Engineering 18 (2): 363-85. https://izlik.org/JA97WD85CF.
EndNote
Desticioğlu B (November 1, 2022) PROJECT PLANNING WITH CPM AND PERT METHODS: EXAMPLE OF DEFENCE INDUSTRY. Journal of Naval Sciences and Engineering 18 2 363–385.
IEEE
[1]B. Desticioğlu, “PROJECT PLANNING WITH CPM AND PERT METHODS: EXAMPLE OF DEFENCE INDUSTRY”, JNSE, vol. 18, no. 2, pp. 363–385, Nov. 2022, [Online]. Available: https://izlik.org/JA97WD85CF
ISNAD
Desticioğlu, Beste. “PROJECT PLANNING WITH CPM AND PERT METHODS: EXAMPLE OF DEFENCE INDUSTRY”. Journal of Naval Sciences and Engineering 18/2 (November 1, 2022): 363-385. https://izlik.org/JA97WD85CF.
JAMA
1.Desticioğlu B. PROJECT PLANNING WITH CPM AND PERT METHODS: EXAMPLE OF DEFENCE INDUSTRY. JNSE. 2022;18:363–385.
MLA
Desticioğlu, Beste. “PROJECT PLANNING WITH CPM AND PERT METHODS: EXAMPLE OF DEFENCE INDUSTRY”. Journal of Naval Sciences and Engineering, vol. 18, no. 2, Nov. 2022, pp. 363-85, https://izlik.org/JA97WD85CF.
Vancouver
1.Beste Desticioğlu. PROJECT PLANNING WITH CPM AND PERT METHODS: EXAMPLE OF DEFENCE INDUSTRY. JNSE [Internet]. 2022 Nov. 1;18(2):363-85. Available from: https://izlik.org/JA97WD85CF