Research Article

Accelerated alkali-silica reaction after a seven-year ASR-dormancy period

Volume: 9 Number: 4 December 31, 2024
EN

Accelerated alkali-silica reaction after a seven-year ASR-dormancy period

Abstract

The ongoing alkali-silica reaction (ASR) in concrete can be halted by dryness, which is important for repairing ASR-suffered concrete structures. Drying of the concrete establishes an ASR-dormancy period until the end of the dryness. The residual expansion of such concrete after the ingress of water—the end of the dormancy period is a significant risk, especially for repair works. In this experimental study, the post-dormancy expansion of various mixtures prepared by eight different Portland cement and three different supplementary cementitious materials (SCM) were tested using an accelerated mortar bar test. After accelerated ASR ex- pansions, an ASR-dormancy period was established by keeping the specimens dry for seven years; the residual ASR expansions of the specimens were tested by the same accelerated method. The effect of pre-dormancy reactions on the residual expansions was discussed through two perspectives. The post-dormancy expansion behavior of mixtures without or with insufficient SCM indicated that expansions were primarily driven by the swelling of old gel, whereas in specimens with sufficient SCM, the dominant mechanism was new gel formation, a result of lower pre-dormancy expansions due to the ASR-mitigating effect of SCMs. Keywords: Alkali silica reaction, cement, durability, supplementary cementitious materials

Keywords

References

  1. 1. Stanton, T. E. (1942). Expansion of concrete through reaction between cement and aggregate. Trans Am Soc Civ Eng, 107(1), 54-84. [CrossRef]
  2. 2. Daidai, T., Torii, K. (2008). A proposal for rehabilitation of ASR-affected bridge piers with fractured steel bars. Proc. of 13th Inter. Conf. on Alkali-aggregate Reaction in Concrete.
  3. 3. Daidai, T., Andrade, O., Torii, K. (2012). The maintenance and rehabilitation techniques for ASR-affected bridge piers with fracture of steel bars. Proc. 14th Inter. Conf. on Alkali-aggregate Reaction in Concrete, Austin, Texas.
  4. 4. Torii, K., Prasetia, I., Minato, T., Ishii, K. (2012). The feature of cracking in prestressed concrete bridge girders deteriorated by alkali-silica reaction. Proc. 14th Inter. Conf. on Alkali-aggregate Reaction in Concrete, Austin, Texas.
  5. 5. Nomura, M., Komastubara, A., Fujimoto, K., Torii, K. (2013). Evaluation of maintenance methods for ASR-damaged structures in Hokuriku district, Japan. Proceedings, Third International Conference on Sustainable Construction Materials and Technologies, Kyoto, Japan.
  6. 6. Luan, Y., Arasawa, T., Mutsuyoshi, H., & Kawana, R. (2021). Repair of alkali-silica reaction-induced cracks using bacteria: Crack recovery and other properties. ACI Mater J, 118(4), 133-142. [CrossRef]
  7. 7. Bakker, J. D. (2008). Control of ASR related risks in the Netherlands. Proceedings of the 13th International Conference on Alkali-Aggregate Reaction in Concrete, Trondheim, Norway, (pp. 16-20).
  8. 8. Multon, S., & Toutlemonde, F. (2010). Effect of moisture conditions and transfers on alkali silica reaction damaged structures. Cement Concr Res, 40(6), 924-934. [CrossRef]

Details

Primary Language

English

Subjects

Construction Materials

Journal Section

Research Article

Early Pub Date

December 30, 2024

Publication Date

December 31, 2024

Submission Date

May 24, 2024

Acceptance Date

November 25, 2024

Published in Issue

Year 2024 Volume: 9 Number: 4

APA
Beglarigale, A. (2024). Accelerated alkali-silica reaction after a seven-year ASR-dormancy period. Journal of Sustainable Construction Materials and Technologies, 9(4), 327-334. https://doi.org/10.47481/jscmt.1608352