COMPARISON OF THERMOECONOMIC COST CALCULATION FOR A BINARY GEOTHERMAL POWER PLANT
Abstract
This
paper presents a comparison of the three thermoeconomic methodologies, SPECO
(Specific exergy costing), MOPSA (Modified productive structure analysis) and
Moran for an existing binary geothermal power plant in western Turkey. Exergy and exergoeconomic analyses of the
Dora II binary geothermal power plant with 9543 kW net power output is carried out by using actual plant data to
evaluate plant performances and thermoeconomic costs. The objective of
the study is to perform the advantages and disadvantages of the presented
thermoeconomic methods with respect to the one other using a binary geothermal
plant data. The presented thermoeconomic methodologies are used to reveal and
compare the cost flows and products interactions between the system components.
The overall energy and exergy efficiencies of the plant are calculated to be
47.3% and 13.5%. The unit exergetic costs of electricity are calculated to be
0.0436 $/kWh for MOPSA method, 0.0367 $/kWh for SPECO method and 0.0355 $/kWh
for MORAN method, respectively.
Keywords
References
- [1] Kanoglu, M., Yilmaz, C. (2013). Thermal Design of Alkaline Water Electrolysis Assisted by Combined Flash Binary Geothermal Power Plant. In ASME 2013 International Mechanical Engineering Congress and Exposition. American Society of Mechanical Engineers.
- [2] Cengel, Y. A., Boles, M. A., (2015). Thermodynamics: an engineering approach, 8th edition.
- [3] Yilmaz, C. (2017). Thermoeconomic modeling and optimization of a hydrogen production system using geothermal energy. Geothermics, 65, 32-43.
- [4] Erkan, K., Holdmann, G., Benoit, W., Blackwell, D. (2008). Understanding the Chena Hot Springs, Alaska, geothermal system using temperature and pressure data from exploration boreholes. Geothermics, 37(6), 565-585.
- [5] Coskun, A., Bolatturk, A., Kanoglu, M. (2014). Thermodynamic and economic analysis and optimization of power cycles for a medium temperature geothermal resource. Energy conversion and management, 78, 39-49.
- [6] Ganjehsarabi, H., Gungor, A., Dincer, I. (2012). Exergetic performance analysis of Dora II geothermal power plant in Turkey. Energy, 46(1), 101-108.
- [7] Zare, V. (2015). A comparative exergoeconomic analysis of different ORC configurations for binary geothermal power plants. Energy Conversion and Management, 105, 127-138.
- [8] Yildirim, D., Ozgener, L. (2012). Thermodynamics and exergoeconomic analysis of geothermal power plants. Renewable and Sustainable Energy Reviews, 16(8), 6438-6454.
Details
Primary Language
English
Subjects
-
Journal Section
Research Article
Authors
Publication Date
June 25, 2018
Submission Date
November 9, 2017
Acceptance Date
January 5, 2018
Published in Issue
Year 2018 Volume: 4 Number: 5
Cited By
Binary power generation system by utilizing solar energy in Malaysia
Ain Shams Engineering Journal
https://doi.org/10.1016/j.asej.2021.11.019