A Project Management Model for Investigation of a Construction Project
Abstract
Various projects are realized
by private sector and public institutions in recent days. Machine, material,
manpower, time and money are the main resources required for these projects.
Since, each one is a cost item, these sources should be used effectively in
order to provide competitive advantage in the project planning process. In this
context, an efficient project management system provides effective usage of resources,
good working environment and timely completion of projects. Critical Path
Method (CPM) and Program Evaluation and Review Technique (PERT) are utilized as
project planning methods in order to determine the completion time of projects.
On the other hand, it can be possible to complete a project earlier using
additional sources with project crashing approach. In this study, initially activities
and durations for a construction project realized in Kocaeli have been
determined. Afterwards, expected completion time, critical activities and
critical path have been determined for this project. In the second phase,
project crashing cost for critical activities has been calculated through a
mathematical model. Thus, the applicability of the project management model has
been revealed.
Keywords
References
- [1] W. Winston, Operations Research Applications and Algorithms, 4th ed., 2003.
- [2] N. Ibadov, Determination of the Risk Factors Impact on the Construction Projects Implementation Using Fuzzy Sets Theory, Acta Physica Polonica A 130(2016) 107-111. 10.12693/APhysPolA.130.107
- [3] L.O. Ugur, A Neuro-Adaptive Learning (NAL) Approach about Costs of Residential Buildings, Acta Physica Polonica A 132(2017) 585-587. 10.12693/APhysPolA.132.585
- [4] A. Recioui, Design and Thinning of Linear and Planar Antenna Arrays Using a Binary Teaching Learning Optimizer, Acta Physica Polonica A 130(2016) 7-8. 10.12693/APhysPolA.130.7
- [5] S. Foldes, F. Soumis, PERT and crashing revisited: Mathematical generalizations, European Journal of Operational Research 64(1993) 286-294. https://doi.org/10.1016/0377-2217(93)90183-N
- [6] M.F. Shipley, A. Korvin, K. Omer, BIFPET methodology versus PERT in project management: fuzzy probability instead of the beta distribution, Journal of Engineering and Technology Management 14(1997) 49-65. https://doi.org/10.1016/S0923-4748(97)00001-5
- [7] S. Gümüsoglu, H. Tütek, An analysis method in project management using primal-dual relationships, International Journal of Project Management 16(1998) 321-327. https://doi.org/10.1016/S0263-7863(97)00057-4
- [8] G.Y. Abbasi, A.M. Mukattash, Crashing PERT networks using mathematical programming, International Journal of Project Management 19(2001) 181-188. https://doi.org/10.1016/S0263-7863(99)00061-7
Details
Primary Language
English
Subjects
-
Journal Section
Research Article
Publication Date
July 2, 2018
Submission Date
April 17, 2018
Acceptance Date
May 14, 2018
Published in Issue
Year 2018 Volume: 4 Number: 2
APA
Çolak, M., Kesik, Ş., Mutman, U., & Aydın Keskin, G. (2018). A Project Management Model for Investigation of a Construction Project. International Journal of Computational and Experimental Science and Engineering, 4(2), 32-36. https://doi.org/10.22399/ijcesen.415944
AMA
1.Çolak M, Kesik Ş, Mutman U, Aydın Keskin G. A Project Management Model for Investigation of a Construction Project. IJCESEN. 2018;4(2):32-36. doi:10.22399/ijcesen.415944
Chicago
Çolak, Murat, Şeyma Kesik, Utkan Mutman, and Gülşen Aydın Keskin. 2018. “A Project Management Model for Investigation of a Construction Project”. International Journal of Computational and Experimental Science and Engineering 4 (2): 32-36. https://doi.org/10.22399/ijcesen.415944.
EndNote
Çolak M, Kesik Ş, Mutman U, Aydın Keskin G (July 1, 2018) A Project Management Model for Investigation of a Construction Project. International Journal of Computational and Experimental Science and Engineering 4 2 32–36.
IEEE
[1]M. Çolak, Ş. Kesik, U. Mutman, and G. Aydın Keskin, “A Project Management Model for Investigation of a Construction Project”, IJCESEN, vol. 4, no. 2, pp. 32–36, July 2018, doi: 10.22399/ijcesen.415944.
ISNAD
Çolak, Murat - Kesik, Şeyma - Mutman, Utkan - Aydın Keskin, Gülşen. “A Project Management Model for Investigation of a Construction Project”. International Journal of Computational and Experimental Science and Engineering 4/2 (July 1, 2018): 32-36. https://doi.org/10.22399/ijcesen.415944.
JAMA
1.Çolak M, Kesik Ş, Mutman U, Aydın Keskin G. A Project Management Model for Investigation of a Construction Project. IJCESEN. 2018;4:32–36.
MLA
Çolak, Murat, et al. “A Project Management Model for Investigation of a Construction Project”. International Journal of Computational and Experimental Science and Engineering, vol. 4, no. 2, July 2018, pp. 32-36, doi:10.22399/ijcesen.415944.
Vancouver
1.Murat Çolak, Şeyma Kesik, Utkan Mutman, Gülşen Aydın Keskin. A Project Management Model for Investigation of a Construction Project. IJCESEN. 2018 Jul. 1;4(2):32-6. doi:10.22399/ijcesen.415944
Cited By
LINEAR PROGRAMMING WITH FUZZY CPM: A CASE STUDY IN CONSTRUCTION SECTOR
Mühendislik Bilimleri ve Tasarım Dergisi
https://doi.org/10.21923/jesd.949954