Evaluation of Performance by Operating Process Improvement Modeling On A Company With Pump Manufacturing
Abstract
There may be more than one element affecting quality and efficiency in the manufacturing organizations. As a result of multiple elements occurring at the same time, permanent losses occur in final production and quality. Both the customer sense of trust and their satisfaction are negatively affected because of those problems.
Failure to achieve targeted levels of quality and productivity in the organization reduces customer satisfaction. Quality and productivity in the organization are affected by inefficiency in resource utilization, bottlenecks in the production and inefficient workflow design within the organization.
This study aims to improve production process in a manufacturer of air operated diaphragm pumps by simulation analysis. Most efficient way of utilizing raw materials, manpower, vehicles and equipment is sought by simulation based process improvement. Discrete-event simulation software (Arena) is used to detect problems in the production process such as: transportation, blockage and/or layout. Simulation is used to experiment with process improvement approaches without making changes in the real-world production system.
Simulation models of the current state and the proposed future state with improvements to the layout of the production system are created. The results from the models were compared with each other and evaluations were made. The future state simulation model utilizes existing resources for process improvement, without the requirement for additional resource acquisition. Comparison of current state model and future state model simulation output data, suggests a 67% increase in the number of products produced per month. It is foreseen that this increase can greatly affect the operational efficiency and future managerial decisions, and suggestions are made for future works.
Keywords
References
- [1] Monks, J., G. (1996) “İşlemler Yönetimi” S. Üreten (2.Bas. Çev.), İstanbul, Nobel Yayıncılık.
- [2] Bozkurt, R. (2003) “Süreç İyileştirme” 3. Basım, An¬kara, MPM.
- [3] Takcı, E.:’Bir İmalat İşletmesinde Simülasyon Yardımıyla Süreç İyileştirme Uygulaması Kayseri Gürkar Tekstil Örneği’, Yüksek Lisans Tezi, Nevşehir Hacı Bektaş Veli Üniversitesi Sosyal Bilimler Enstitüsü, Nevşehir, Türkiye, (2013).
- [4] Yurdakul, M.;Eşkin, S.;İç, Yusuf T.İ.:’ Bir İmalat Sisteminin Yerleşim Düzeninin İyileştirilmesi’, Gazi Üniversitesi Mühendislik Fakültesi, Başkent Üniversitesi Mühendislik Fakültesi,Ankara, Türkiye, (2009).
- [5] Özateş, M.;Şahin, M.; Şenol, S.; Terzi, F.; Yörükoğlu, S.; Köksal, G.; Serin, Y.:’ Düşük Hacimli Üretim İçin Kalite Kontrol Sistemi Tasarımı’, Orta Doğu Teknik Üniversitesi Mühendislik Fakültesi, Ankara, Türkiye, (2012).
- [6] Yurdakul, M.;Türkbaş, S.; Altınova, S.: ’ Bir İmalat Tesisinde Toplam Verimli Bakım (TVB) Uygulaması’, Gazi Üniversitesi Mühendislik-Mimarlık Fakültesi, Ankara, Mercedes-Benz Türk A.Ş. Aksaray Fabrikası, Aksaray, (2008).
- [7] Oran, A.:’ Talaşlı İmalat Optimizasyonunda Metodik Yaklaşım ve Sektörel Bir Altı Sigma Proje Uygulaması’, BOSCH San. ve Tic. A.Ş. Teknik Fonksiyonlar 1 Departmanı, Bursa, Türkiye, (2012).
- [8] Şahin, Ş.; Öztürk, F.:’ İmalat Süreçlerindeki Problemlere Optimum Çözüm Arama Ve Bir Uygulama’, Uludağ Üniversitesi Mühendislik-Mimarlık Fakültesi, Bursa, (2009).
Details
Primary Language
English
Subjects
Engineering
Journal Section
Research Article
Authors
Ahmet Talat İnan
*
This is me
0000-0003-2720-5711
Türkiye
Publication Date
November 1, 2019
Submission Date
April 16, 2019
Acceptance Date
October 15, 2019
Published in Issue
Year 2019 Volume: 31 Number: 4