Research Article

Identification of Dispute Sources in the Construction Industry via Court Files

Volume: 34 Number: 2 March 1, 2023
EN

Identification of Dispute Sources in the Construction Industry via Court Files

Abstract

Contracting parties generally tend to resolve their disputes through the litigation process. The lengthy litigation process reduces the belief among the parties that the disputes are resolved peacefully, and this destabilizes the sustainable structure of the construction industry where disputes are very common. Determining the most common sources of disputes in construction lawsuits is very important in terms of taking necessary precautions beforehand. Additionally, increasing the competency levels of construction and judicial actors regarding construction processes is extremely important in terms of making the judicial process more efficient and faster. Therefore, this study aims to reveal the most frequent dispute sources in the construction industry, the competency levels of judicial actors including expert witnesses and the average duration of the construction-related litigation process for the superior courts. Hence, 346 construction-related lawsuits conducted between 2018 and 2021 were examined via content analysis to classify the common themes. Lawsuits were investigated via the official websites of Courts of Cassation and National Judicial Network Information System (UYAP). Next, the frequency analysis was conducted to detect the significance of each theme via SPSS software. It is highly believed that this study will enable the decision-makers to take necessary precautions before the dispute occurs as well as improve the dispute resolution process in the construction industry. Projects related to superstructure works constituted the majority of the disputes ending up with the judicial process. Additionally, the majority of the disputes detected from lawsuits resulted from “Debit and Credit” related issues. Moreover, the litigation process was also detected as a very lengthy process. Furthermore, it is detected that majority of the lawsuits were rejected by the Courts of Cassation due to inadequacies of the competency levels of the judicial actors.

Keywords

References

  1. E. Taş and Ö. Fırtına, “The use of dispute review boards in construction projects: A comparison of Turkey, UK and US,” A|Z ITU J. Fac. Archit., vol. 12, no. 2, pp. 187–204, 2015, [Online]. Available: https://www.journalagent.com/itujfa/pdfs/ITUJFA-74745-THEORY_ARTICLES-TAS.pdf.
  2. V. Kaya, Ö. Yalçınkaya, and İ. Hüseyni, “Ekonomik Büyümede İnşaat Sektörünün Rolü:Türkiye Örneği (1987-2010),” Atatürk Üniversitesi İktisadi ve İdari Bilim. Derg., vol. 27, no. 4, pp. 148–167, 2013, [Online]. Available: https://dergipark.org.tr/tr/download/article-file/30518.
  3. Oxfordbusinessgroup, “Turkey’s Construction Sector to Maintain Its Significant Role in the Economy, with Several Large Projects under Way,” 2015. https://www.oxfordbusinessgroup.com/turkey-2015 (accessed Nov. 20, 2019).
  4. M. Cevikbas, O. Okudan, and Z. Işık, “Identification and assessment of disruption claim management risks in construction projects: a life cycle-based approach,” Eng. Constr. Archit. Manag., 2022, doi: 10.1108/ECAM-05-2022-0470.
  5. D. Artan Ilter and G. Bakioglu, “Modeling the Relationship between Risk and Dispute in Subcontractor Contracts,” J. Leg. Aff. Disput. Resolut. Eng. Constr., vol. 10, no. 1, p. 04517022, 2018, doi: 10.1061/(ASCE)LA.1943-4170.0000246.
  6. G. Başyiğit, “Kat Karşiliği İnşaat Sözleşmeleri ve Kat Karşiliği Standart İnşaat Sözleşme Maddeleri Önerisi,” Yıldız Teknik Üniversitesi, 2012.
  7. D. Arditi and T. Pulket, “Predicting the Outcome of Construction Litigation Using Boosted Decision Trees,” J. Comput. Civ. Eng., vol. 19, no. 4, pp. 387–393, Oct. 2005, doi: 10.1061/(ASCE)0887-3801(2005)19:4(387).
  8. D. Ilter, “Identification of the relations between dispute factors and dispute categories in construction projects,” Int. J. Law Built Environ., vol. 4, no. 1, pp. 45–59, 2012, doi: 10.1108/17561451211211732.

Details

Primary Language

English

Subjects

Civil Engineering

Journal Section

Research Article

Publication Date

March 1, 2023

Submission Date

July 2, 2022

Acceptance Date

December 16, 2022

Published in Issue

Year 2023 Volume: 34 Number: 2

APA
Cevikbas, M. (2023). Identification of Dispute Sources in the Construction Industry via Court Files. Turkish Journal of Civil Engineering, 34(2), 57-76. https://doi.org/10.18400/tjce.1224425
AMA
1.Cevikbas M. Identification of Dispute Sources in the Construction Industry via Court Files. TJCE. 2023;34(2):57-76. doi:10.18400/tjce.1224425
Chicago
Cevikbas, Murat. 2023. “Identification of Dispute Sources in the Construction Industry via Court Files”. Turkish Journal of Civil Engineering 34 (2): 57-76. https://doi.org/10.18400/tjce.1224425.
EndNote
Cevikbas M (March 1, 2023) Identification of Dispute Sources in the Construction Industry via Court Files. Turkish Journal of Civil Engineering 34 2 57–76.
IEEE
[1]M. Cevikbas, “Identification of Dispute Sources in the Construction Industry via Court Files”, TJCE, vol. 34, no. 2, pp. 57–76, Mar. 2023, doi: 10.18400/tjce.1224425.
ISNAD
Cevikbas, Murat. “Identification of Dispute Sources in the Construction Industry via Court Files”. Turkish Journal of Civil Engineering 34/2 (March 1, 2023): 57-76. https://doi.org/10.18400/tjce.1224425.
JAMA
1.Cevikbas M. Identification of Dispute Sources in the Construction Industry via Court Files. TJCE. 2023;34:57–76.
MLA
Cevikbas, Murat. “Identification of Dispute Sources in the Construction Industry via Court Files”. Turkish Journal of Civil Engineering, vol. 34, no. 2, Mar. 2023, pp. 57-76, doi:10.18400/tjce.1224425.
Vancouver
1.Murat Cevikbas. Identification of Dispute Sources in the Construction Industry via Court Files. TJCE. 2023 Mar. 1;34(2):57-76. doi:10.18400/tjce.1224425

Cited By