PROJECT SCHEDULING AND STAFF ALLOCATION PROBLEM WITH TIME-DEPENDENT LEARNING EFFECT: A MIXED INTEGER NON-LINEAR PROGRAMMING APPROACH

Volume: 20 Number: 3 September 26, 2019
EN

PROJECT SCHEDULING AND STAFF ALLOCATION PROBLEM WITH TIME-DEPENDENT LEARNING EFFECT: A MIXED INTEGER NON-LINEAR PROGRAMMING APPROACH

Abstract

This paper proposes a mixed integer non-linear programming (MINLP) for project scheduling and staff allocation problem with time-dependent learning effect considering task similarities for learning. Resources of a project, especially staffs, can learn from previous tasks if those tasks and the current task are similar. Considering similarities among tasks for each staff can produce a more realistic schedule for a project. The objective function of the proposed problem is to minimize project completion time. The learning effect in this paper is dependent on the time when the project staff starts to do that task. If a project staff does repetitive and/or similar tasks then that staff can get experience and do tasks faster than planned durations. Therefore, task sequence is essential to assign tasks to project staffs in order to minimize project completion time by considering task similarities in view of learning.

Keywords

Time-dependent learning effect,Project scheduling,Mixed integer non-linear programming,Staff allocation

References

  1. [1] Wright TP. Factors Affecting the Cost of Airplanes. J Aeronaut Sci 1936; 3: 122–128.
  2. [2] Biskup D. Single-machine scheduling with learning considerations. Eur J Oper Res 1999; 115: 173–178.
  3. [3] Kuo WH, Yang DL. Minimizing the total completion time in a single-machine scheduling problem with a time-dependent learning effect. Eur J Oper Res 2006; 174: 1184–1190.
  4. [4] Arık OA, Toksarı MD. Multi-objective fuzzy parallel machine scheduling problems under fuzzy job deterioration and learning effects. Int J Prod Res 2018; 56: 2488–2505.
  5. [5] Arık OA, Toksarı MD. Fuzzy Parallel Machine Scheduling Problem Under Fuzzy Job Deterioration and Learning Effects With Fuzzy Processing Times in Advanced Fuzzy Logic Approaches in Engineering Science, M. Ram, Ed. IGI Global, 2019, pp. 49–67.
  6. [6] Arık OA, Toksari MD. Fuzzy chance constrained programming technique for single machine earliness/tardiness scheduling problem under effects of fuzzy learning and deterioration. Sak. Univ J Sci 2018; 22(2): 652–662.
  7. [7] Toksarı MD, Arık OA. Single machine scheduling problems under position-dependent fuzzy learning effect with fuzzy processing times. J Manuf Syst, 2017; 45:159-179.
  8. [8] Shtub A, LeBlanc LJ, Cai Z. Scheduling programs with repetitive projects: A comparison of a simulated annealing, a genetic and a pair-wise swap algorithm. Eur J Oper Res 1996; 88: 124–138.
  9. [9] Ash R, Smith-Daniels DE. The effects of learning, forgetting, and relearning on decision rule performance in multi project scheduling. Decis Sci 1999; 30: 47–79.
  10. [10] Arditi D, Tokdemir OB, Suh K. Effect of learning on line-of-balance scheduling. Int J Proj Manag 2001; 19: 265–277.
APA
Arık, O. A. (2019). PROJECT SCHEDULING AND STAFF ALLOCATION PROBLEM WITH TIME-DEPENDENT LEARNING EFFECT: A MIXED INTEGER NON-LINEAR PROGRAMMING APPROACH. Eskişehir Technical University Journal of Science and Technology A - Applied Sciences and Engineering, 20(3), 204-215. https://doi.org/10.18038/estubtda.624291
AMA
1.Arık OA. PROJECT SCHEDULING AND STAFF ALLOCATION PROBLEM WITH TIME-DEPENDENT LEARNING EFFECT: A MIXED INTEGER NON-LINEAR PROGRAMMING APPROACH. Estuscience - Se. 2019;20(3):204-215. doi:10.18038/estubtda.624291
Chicago
Arık, Oğuzhan Ahmet. 2019. “PROJECT SCHEDULING AND STAFF ALLOCATION PROBLEM WITH TIME-DEPENDENT LEARNING EFFECT: A MIXED INTEGER NON-LINEAR PROGRAMMING APPROACH”. Eskişehir Technical University Journal of Science and Technology A - Applied Sciences and Engineering 20 (3): 204-15. https://doi.org/10.18038/estubtda.624291.
EndNote
Arık OA (September 1, 2019) PROJECT SCHEDULING AND STAFF ALLOCATION PROBLEM WITH TIME-DEPENDENT LEARNING EFFECT: A MIXED INTEGER NON-LINEAR PROGRAMMING APPROACH. Eskişehir Technical University Journal of Science and Technology A - Applied Sciences and Engineering 20 3 204–215.
IEEE
[1]O. A. Arık, “PROJECT SCHEDULING AND STAFF ALLOCATION PROBLEM WITH TIME-DEPENDENT LEARNING EFFECT: A MIXED INTEGER NON-LINEAR PROGRAMMING APPROACH”, Estuscience - Se, vol. 20, no. 3, pp. 204–215, Sept. 2019, doi: 10.18038/estubtda.624291.
ISNAD
Arık, Oğuzhan Ahmet. “PROJECT SCHEDULING AND STAFF ALLOCATION PROBLEM WITH TIME-DEPENDENT LEARNING EFFECT: A MIXED INTEGER NON-LINEAR PROGRAMMING APPROACH”. Eskişehir Technical University Journal of Science and Technology A - Applied Sciences and Engineering 20/3 (September 1, 2019): 204-215. https://doi.org/10.18038/estubtda.624291.
JAMA
1.Arık OA. PROJECT SCHEDULING AND STAFF ALLOCATION PROBLEM WITH TIME-DEPENDENT LEARNING EFFECT: A MIXED INTEGER NON-LINEAR PROGRAMMING APPROACH. Estuscience - Se. 2019;20:204–215.
MLA
Arık, Oğuzhan Ahmet. “PROJECT SCHEDULING AND STAFF ALLOCATION PROBLEM WITH TIME-DEPENDENT LEARNING EFFECT: A MIXED INTEGER NON-LINEAR PROGRAMMING APPROACH”. Eskişehir Technical University Journal of Science and Technology A - Applied Sciences and Engineering, vol. 20, no. 3, Sept. 2019, pp. 204-15, doi:10.18038/estubtda.624291.
Vancouver
1.Oğuzhan Ahmet Arık. PROJECT SCHEDULING AND STAFF ALLOCATION PROBLEM WITH TIME-DEPENDENT LEARNING EFFECT: A MIXED INTEGER NON-LINEAR PROGRAMMING APPROACH. Estuscience - Se. 2019 Sep. 1;20(3):204-15. doi:10.18038/estubtda.624291