Measuring the Effects of Different Factors on Activity Times in Wind Power Projects under Fuzzy Set Theory
Abstract
In this study, it is aimed to determine the project completion time in a more realistic way by analyzing the effects of uncertainties experienced in wind power projects. For this purpose, a method was applied to calculate the project completion time under fuzzy set theory by including the risk factors in the relevant activity durations of an international company's wind power project. CPM and F-PERT methods were also applied to show the robustness of the applied method, and these three methods' results were benchmarked against the actual time of the project. The result of the study showed that a more realistic estimate of the project completion time can be determined with the applied method, in which all the factors affecting the duration of the activities are included, experts’ opinions are taken into consideration, and historical data is used. In this study, in which the risk factors for wind power projects are examined in detail and suggestions for improvement are put forward, a customized roadmap for the management of all types of projects, particularly wind power projects, is intended to serve decision makers.
Keywords
References
- [1] Haghighi, M.H., Mousavi, S.M., Antuchevıčıenė, J., and Mohagheghi, V., “A new analytical methodology to handle time-cost trade-off problem with considering quality loss cost under interval-valued fuzzy uncertainty”, Technological and Economic Development of Economy, 25(2): 277-299, (2019). DOI: https://doi.org/10.3846/tede.2019.8422.
- [2] Kelley, J.E., “Critical path planning and scheduling – Mathematical basis”, Operations Research, 9(3): 296-320, (1961). DOI: https://doi.org/10.1287/opre.9.3.296.
- [3] Zammori, F.A., Braglia, M., and Frosolini, M., “A fuzzy multi-criteria approach for critical path definition”, International Journal of Project Management, 27(3): 278–291, (2009). DOI: https://doi.org/10.1016/j.ijproman.2008.03.006.
- [4] Beaula, T., and Vijaya, V., “A new method to find critical path from multiple paths in project networks”, International Journal of Fuzzy Mathematical Archive, 9(2): 235-243, (2015). DOI: http://dx.doi.org/10.22457/ijfma.v16n1a9.
- [5] Malcolm, D.G., Roseboom, J.H., Clark, C.E., and Fazar, W., “Application of a technique for research and development project evaluation”, Operations Research, 7(5): 646–669, (1959). DOI: https://doi.org/10.1287/opre.7.5.646.
- [6] Farnum, N.R., and Stanton, L.W., “Some results concerning the estimation of beta distribution parameters in PERT”, Journal of the Operational Research Society, 38(3): 287-290, (1987). DOI: https://doi.org/10.1057/jors.1987.45.
- [7] Ammar, M.A., and Abd-ElKhalek, S.I. “Criticality measurement in fuzzy project scheduling”, International Journal of Construction Management, 22(2): 252-261, (2019). DOI: https://doi.org/10.1080/15623599.2019.1619226.
- [8] Chanas, S., Dubois, D., and Zielinski, P., “On the sure criticality of asks in activity networks with imprecise durations”, IEEE Transactions on Systems, Man, and Cybernetics, Part B, 32(4): 393–407, (2002). DOI: https://doi.org/10.1109/TSMCB.2002.1018760.
Details
Primary Language
English
Subjects
Fuzzy Computation, Planning and Decision Making, Operations Research İn Mathematics, Wind Energy Systems, Industrial Engineering
Journal Section
Research Article
Authors
Early Pub Date
August 4, 2025
Publication Date
September 1, 2025
Submission Date
December 11, 2024
Acceptance Date
June 5, 2025
Published in Issue
Year 2025 Volume: 38 Number: 3
APA
Kaya Samut, P. (2025). Measuring the Effects of Different Factors on Activity Times in Wind Power Projects under Fuzzy Set Theory. Gazi University Journal of Science, 38(3), 1374-1386. https://doi.org/10.35378/gujs.1599844
AMA
1.Kaya Samut P. Measuring the Effects of Different Factors on Activity Times in Wind Power Projects under Fuzzy Set Theory. Gazi University Journal of Science. 2025;38(3):1374-1386. doi:10.35378/gujs.1599844
Chicago
Kaya Samut, Pınar. 2025. “Measuring the Effects of Different Factors on Activity Times in Wind Power Projects under Fuzzy Set Theory”. Gazi University Journal of Science 38 (3): 1374-86. https://doi.org/10.35378/gujs.1599844.
EndNote
Kaya Samut P (September 1, 2025) Measuring the Effects of Different Factors on Activity Times in Wind Power Projects under Fuzzy Set Theory. Gazi University Journal of Science 38 3 1374–1386.
IEEE
[1]P. Kaya Samut, “Measuring the Effects of Different Factors on Activity Times in Wind Power Projects under Fuzzy Set Theory”, Gazi University Journal of Science, vol. 38, no. 3, pp. 1374–1386, Sept. 2025, doi: 10.35378/gujs.1599844.
ISNAD
Kaya Samut, Pınar. “Measuring the Effects of Different Factors on Activity Times in Wind Power Projects under Fuzzy Set Theory”. Gazi University Journal of Science 38/3 (September 1, 2025): 1374-1386. https://doi.org/10.35378/gujs.1599844.
JAMA
1.Kaya Samut P. Measuring the Effects of Different Factors on Activity Times in Wind Power Projects under Fuzzy Set Theory. Gazi University Journal of Science. 2025;38:1374–1386.
MLA
Kaya Samut, Pınar. “Measuring the Effects of Different Factors on Activity Times in Wind Power Projects under Fuzzy Set Theory”. Gazi University Journal of Science, vol. 38, no. 3, Sept. 2025, pp. 1374-86, doi:10.35378/gujs.1599844.
Vancouver
1.Pınar Kaya Samut. Measuring the Effects of Different Factors on Activity Times in Wind Power Projects under Fuzzy Set Theory. Gazi University Journal of Science. 2025 Sep. 1;38(3):1374-86. doi:10.35378/gujs.1599844