Assessment of Qualification Criteria Described in Public Procurement Law Code 4734 in Construction Works by Analytic Hierarchy Process (AHP)
Abstract
Turkish public procurement law and secondary regulations describes tender evaluation in detail. In this system, bidders’ capabilities on each qualification criteria are evaluated either as satisfied or not satisfied. This method is criticized as incomplete and lacking consideration in terms of the contractor’s ability to achieve simultaneously, time, cost, quality and safety standards. In this study, as a first step in tender evaluation, each qualification criteria is put into tender evaluation making tender evaluation a multi criteria decision making problem and group AHP method is used to identify the weights of qualification criteria already in use.
Keywords
References
- [1]. Nieto-Morote A. and Ruz-Villa. F., “A fuzzy multi-criteria decision making model for construction contractor prequalification”, Automation in Construction, 25; 8-19, (2012).
- [2]. Burdurlu, E. and Ejder, E. “Location choice for furniture industry firms by using analytic hierarchy process (AHP) method”, Gazi University Journal of Science, 16(2): 369-373, (2003).
- [3]. Vaidya, O. and Kumar, S., “Analytic hierarchy process: An overview of applications”, European Journal of Operational Research, 169: 1-29, (2006).
- [4]. Arpacıoglu, U. and Ersoy, H. Y., “Daylight and energy oriented architecture design support model”, Gazi University Journal of Science, 26(2): 331-346, (2013).
- [5]. Aminbakhsh, S., Gunduz, M. and Sonmez. R., “Safety risk assessment using analytic hierarchy process (AHP) during planning and budgeting of construction projects”, Journal of Safety Research, (46): 99-105, (2013).
- [6]. Uğur, L. O. and Baykan, U. “A model proposal for wall material selection decisions by using analytic hierarchy process (AHP)”, Acta Physica Polonica A, 132(3): 577-579, (2017).
- [7]. Tama, M. C. and Tummalab V. R., “An application of the AHP in vendor selection of a telecommunications system”, International Journal of Management Science, (29): 171-182, (2001).
- [8]. El-Sawalhi, N., Eaton, D. and Rustom, R., “Establishing relative weights for contractor prequalification criteria in a pre-qualification evaluation model”, The 7th International Postgraduate Research Conference, Manchester, pp. 43-53, (2007).
Details
Primary Language
English
Subjects
Engineering
Journal Section
Research Article
Authors
İbrahim Ozyurek
GAZI UNIVERSITY, FACULTY OF TECHNOLOGY, DEPARTMENT OF CIVIL ENGINEERING
Türkiye
Mursel Erdal
0000-0002-9338-6162
Türkiye
Publication Date
June 1, 2018
Submission Date
January 12, 2018
Acceptance Date
March 13, 2018
Published in Issue
Year 2018 Volume: 31 Number: 2