Analysis of the Time-Cost Changes in the Origin of New Labor Inclusion When Construction Projects' Planning with Network Diagrams

Year 2014, Volume: 2 Issue: 2, 362 - 373, 05.09.2014

Abstract

In this study, the Düzce TOKI Housing Project which is the 8 units of type B blocks complexs’ construction costs, CPM prepared with work schedules, manpower, the relevant year’s inflation and interest value based on the duration of the project Desiner In case of costs , the value on the basis of were investigated. Work within the time specified in the contract (16 months) in the case of the completion of labor costs, monthly income and expenses, inflation and interest rates are calculated. Job completion time of 12 months, 10 months, 8 months and 6 months withdrawal if the project is worth the cost of the labor force entourage, monthly income and expenses, inflation and interest rate changes based on the condition, the values were discussed. To do this, each time the corresponding work programs organized into abbreviation, which require increased labor costs and time drawn diagrams about calculating cost comparisons are made. A project investment while planning; different conditions, different and to plan and each planning time, resources and costs by analysis of the rational to prefer, the findings also support the macro and micro scales, the most appropriate would be the way the idea has been reinforced.

İnşaat Projelerinin Ağ Diyagramlarıyla Planlanmasında Süre-Maliyet Değişimlerinin Yeni İşgücü Eklenmesi Orijininde Analizi

Year 2014, Volume: 2 Issue: 2, 362 - 373, 05.09.2014

Abstract

Bu çalışmada Düzce ili TOKİ Toplu Konut Projesi’nde 8 adet B tipi bloğundan oluşan kompleksin inşaat maliyeti; CPM ile hazırlanan iş programları, iş gücü, ilgili yıl enflasyon ve faiz değerleri esas alınarak proje süresinin değişimi halinde maliyetlerin alacağı değerler bazında incelenmiştir. İşin sözleşmesinde belirtilen sürede (16 ay) tamamlanması durumundaki iş gücü maliyeti, aylık gelir-giderler, enflasyon ve faiz değerleri hesaplanmıştır. İşin tamamlanma süresinin 12 aya, 10 aya, 8 aya, ve 6 aya çekilmesi halinde proje maliyeti değerlerinin; iş gücü maiyetleri, aylık gelir-giderler, enflasyon ve faiz değişimi durumuna göre aldığı değerler irdelenmiştir. Bunun için her süre kısaltması haline karşılık gelen iş programları düzenlenmiş, artış gerektiren iş gücü maliyetleri hesaplanarak ilgili diyagramlar çizilmiş ve süre-maliyet karşılaştırmaları yapılmıştır. Bir projenin yatırım planlaması yapılırken; farklı koşullara göre farklı planlamaların yapılması ve her planlamanın zaman, kaynak ve maliyet analizlerinin yapılarak en rasyonel olanın tercih edilmesinin; edinilen bulguların da desteği ile makro ve mikro ölçeklerde en uygun yol olacağı fikri pekiştirilmiştir.

There are 0 citations in total.

Details

Primary Language Turkish
Subjects Engineering
Journal Section Articles
Authors

Latif Onur Uğur This is me

Ayçin Erdal This is me

Publication Date September 5, 2014
Published in Issue Year 2014 Volume: 2 Issue: 2

Cite

APA Uğur, L. O., & Erdal, A. (2014). İnşaat Projelerinin Ağ Diyagramlarıyla Planlanmasında Süre-Maliyet Değişimlerinin Yeni İşgücü Eklenmesi Orijininde Analizi. Duzce University Journal of Science and Technology, 2(2), 362-373.
AMA Uğur LO, Erdal A. İnşaat Projelerinin Ağ Diyagramlarıyla Planlanmasında Süre-Maliyet Değişimlerinin Yeni İşgücü Eklenmesi Orijininde Analizi. DUBİTED. June 2014;2(2):362-373.
Chicago Uğur, Latif Onur, and Ayçin Erdal. “İnşaat Projelerinin Ağ Diyagramlarıyla Planlanmasında Süre-Maliyet Değişimlerinin Yeni İşgücü Eklenmesi Orijininde Analizi”. Duzce University Journal of Science and Technology 2, no. 2 (June 2014): 362-73.
EndNote Uğur LO, Erdal A (June 1, 2014) İnşaat Projelerinin Ağ Diyagramlarıyla Planlanmasında Süre-Maliyet Değişimlerinin Yeni İşgücü Eklenmesi Orijininde Analizi. Duzce University Journal of Science and Technology 2 2 362–373.
IEEE L. O. Uğur and A. Erdal, “İnşaat Projelerinin Ağ Diyagramlarıyla Planlanmasında Süre-Maliyet Değişimlerinin Yeni İşgücü Eklenmesi Orijininde Analizi”, DUBİTED, vol. 2, no. 2, pp. 362–373, 2014.
ISNAD Uğur, Latif Onur - Erdal, Ayçin. “İnşaat Projelerinin Ağ Diyagramlarıyla Planlanmasında Süre-Maliyet Değişimlerinin Yeni İşgücü Eklenmesi Orijininde Analizi”. Duzce University Journal of Science and Technology 2/2 (June 2014), 362-373.
JAMA Uğur LO, Erdal A. İnşaat Projelerinin Ağ Diyagramlarıyla Planlanmasında Süre-Maliyet Değişimlerinin Yeni İşgücü Eklenmesi Orijininde Analizi. DUBİTED. 2014;2:362–373.
MLA Uğur, Latif Onur and Ayçin Erdal. “İnşaat Projelerinin Ağ Diyagramlarıyla Planlanmasında Süre-Maliyet Değişimlerinin Yeni İşgücü Eklenmesi Orijininde Analizi”. Duzce University Journal of Science and Technology, vol. 2, no. 2, 2014, pp. 362-73.
Vancouver Uğur LO, Erdal A. İnşaat Projelerinin Ağ Diyagramlarıyla Planlanmasında Süre-Maliyet Değişimlerinin Yeni İşgücü Eklenmesi Orijininde Analizi. DUBİTED. 2014;2(2):362-73.