Computation of Critical Path Probabilities by Modified PERT
Abstract
Keywords
References
- Ahuja, H. N., and Nandakumar, V. (1985). Simulation model to forecast project completion time. Journal of construction engineering and management, 111(4), 325-342.
- Moder, J. J., Phillips C. R., and Davis E. W. (1983), Project management with CPM, PERT and precedence diagramming, 3rd Edition, Van Nostrand Reinhold Company, New York.
- Ang, A. H., Chaker, A. A., and Abdelnour, J. (1975). Analysis of activity networks under uncertainty. Journal of the Engineering Mechanics Division, 101(4), 373-387.
- Taroun, A. (2014). Towards a better modelling and assessment of construction risk: Insights from a literature review. International journal of Project management, 32(1), 101-115.
- Helton, J. C. (1993). Uncertainty and sensitivity analysis techniques for use in performance assessment for radioactive waste disposal. Reliability Engineering & System Safety, 42(2-3), 327-367.
- Cheah, C. Y., and Liu, J. (2006). Valuing governmental support in infrastructure projects as real options using Monte Carlo simulation. Construction management and economics, 24(5), 545-554.
- Khamooshi, H., and Cioffi, D. F. (2012). Uncertainty in task duration and cost estimates: Fusion of probabilistic forecasts and deterministic scheduling. Journal of construction engineering and management, 139(5), 488-497.
- Tao, L., Wu, D., Liu, S., and Lambert, J. H. (2017). Schedule risk analysis for new-product development: The GERT method extended by a characteristic function. Reliability Engineering & System Safety, 167, 464-473.
Details
Primary Language
English
Subjects
Engineering
Journal Section
Research Article
Authors
Onder Bettemir
*
0000-0002-5692-7708
Türkiye
Publication Date
September 1, 2020
Submission Date
August 27, 2019
Acceptance Date
April 9, 2020
Published in Issue
Year 2020 Volume: 33 Number: 3