A Case Study on Reducing Setup Time Using SMED on a Turning Line

Volume: 35 Number: 1 March 1, 2022
EN

A Case Study on Reducing Setup Time Using SMED on a Turning Line

Abstract

Today, manufacturers must meet customer demands in a shorter time with the best quality and lowest cost to survive in competitive environment. One way to achieve this is to reduce production costs by eliminating waste activities in a production system. Machine adjustment processes are the activities that do not create value, and Single Minute Exchange of Dies (SMED), lean manufacturing tool, has been developed to reduce these activities. In this paper we have performed a case study in a bearing manufacturing company to reduce the machine setup time on turning line using the SMED. The emphasis is given to both transferring internal activities into external ones as many as possible and minimizing the internal ones. The main results attained from the study indicate that the machine setup times were reduced more than 45% for the turning line. Consequently, machine capacities can be significantly increased by the application of SMED method.

Keywords

Supporting Institution

Destekleyen kurum yok.

Project Number

Projeden üretilmemiştir.

References

  1. [1] Dave, Y., Sohani, N., “Single Minute Exchange of Dies: Literature Review”, International Journal of Lean Thinking, 3(2): 27–37, (2012).
  2. [2] Chong, M.Y., Chin, J.F., Loh, W.P., “Lean Incipience Spiral Model for Small and Medium Enterprises”, International Journal of Industrial Engineering: Theory, Applications and Practice, 20(7-8): 487–501, (2013).
  3. [3] Sherali, H.D., Van Goubergen, D., Van Landeghem, H., “A quantitative approach for scheduling activities to reduce set-up in multiple machine lines”, European Journal of Operational Research, 187(3): 1224-1237, (2008).
  4. [4] Ulutaş, B., “An application of SMED Methodology”, World Academy of Science, Engineering and Technology, 5(7): 63–66, (2011).
  5. [5] Pellegrini, S., Shetty, D., Manzione, L., “Study and Implementation of Single Minute Exchange of Die (SMED) Methodology in a Setup Reduction Kaizen”, Proceedings of the 3rd International Conference on Industrial Engineering and Operations Management, İstanbul, Türkiye, July 3-6, 2353–2363, (2012).
  6. [6] Okur, A.S., Yalın üretim: 2000'li yıllara doğru Türkiye sanayii için yapılanma modeli, Söz Yayın Oyunajans, Türkiye, (1997).
  7. [7] Van Goubergen, D., Van Landeghem, H., “Rules for integrating fast changeover capabilities into new equipment design”, Robotics and Computer-Integrated Manufacturing, 18(3-4): 205–214, (2002).
  8. [8] Trovinger, S.C., Bohn, R.E., “Setup Time Reduction for Electronics Assembly: Combining Simple (SMED) and IT‐Based Methods”, Production and Operations Management, 14(2): 205–217, (2005).

Details

Primary Language

English

Subjects

Engineering

Journal Section

Research Article

Publication Date

March 1, 2022

Submission Date

May 12, 2020

Acceptance Date

April 13, 2021

Published in Issue

Year 2022 Volume: 35 Number: 1

APA
Şahin, R., & Koloğlu, A. (2022). A Case Study on Reducing Setup Time Using SMED on a Turning Line. Gazi University Journal of Science, 35(1), 60-71. https://doi.org/10.35378/gujs.735969
AMA
1.Şahin R, Koloğlu A. A Case Study on Reducing Setup Time Using SMED on a Turning Line. Gazi University Journal of Science. 2022;35(1):60-71. doi:10.35378/gujs.735969
Chicago
Şahin, Ramazan, and Aycan Koloğlu. 2022. “A Case Study on Reducing Setup Time Using SMED on a Turning Line”. Gazi University Journal of Science 35 (1): 60-71. https://doi.org/10.35378/gujs.735969.
EndNote
Şahin R, Koloğlu A (March 1, 2022) A Case Study on Reducing Setup Time Using SMED on a Turning Line. Gazi University Journal of Science 35 1 60–71.
IEEE
[1]R. Şahin and A. Koloğlu, “A Case Study on Reducing Setup Time Using SMED on a Turning Line”, Gazi University Journal of Science, vol. 35, no. 1, pp. 60–71, Mar. 2022, doi: 10.35378/gujs.735969.
ISNAD
Şahin, Ramazan - Koloğlu, Aycan. “A Case Study on Reducing Setup Time Using SMED on a Turning Line”. Gazi University Journal of Science 35/1 (March 1, 2022): 60-71. https://doi.org/10.35378/gujs.735969.
JAMA
1.Şahin R, Koloğlu A. A Case Study on Reducing Setup Time Using SMED on a Turning Line. Gazi University Journal of Science. 2022;35:60–71.
MLA
Şahin, Ramazan, and Aycan Koloğlu. “A Case Study on Reducing Setup Time Using SMED on a Turning Line”. Gazi University Journal of Science, vol. 35, no. 1, Mar. 2022, pp. 60-71, doi:10.35378/gujs.735969.
Vancouver
1.Ramazan Şahin, Aycan Koloğlu. A Case Study on Reducing Setup Time Using SMED on a Turning Line. Gazi University Journal of Science. 2022 Mar. 1;35(1):60-71. doi:10.35378/gujs.735969

Cited By