Early Estimation of Sewerage Line Costs with Regression Analysis

Volume: 35 Number: 3 September 1, 2022
EN

Early Estimation of Sewerage Line Costs with Regression Analysis

Abstract

In Turkey, an average of 450 sewer line tenders are made annually and the total line length of these works is approximately 11000000 m. It is very important for both the investor and the contractor to know the costs of the sewer networks with such a large business volume. In this study, models are developed for early estimation of sewage line costs by the regression analysis method. Data belonging to 182 sewer line projects were used in the development of the models. Data on pipe diameter, line length, excavation depth, manhole amount, excavation amount, filling amount, filling type, shoring type, excavation class and real cost parameters were determined through the projects. Correlations between the determined parameters were specified and the parameters suitable for regression analysis were selected. As a result; among the developed estimation models, the equation using all selected parameters with a correlation coefficient of R² = 0.911 gave the most successful result.

Keywords

References

  1. [1] Topçu, G., “Cost-related operations in the building production process: estimation, planning, control”, MS Thesis, İstanbul Technical University, İstanbul, 25-32, (1989).
  2. [2] Uğur, L.O., Kanıt, R., Erdal, H., Namlı, E., Erdal, H.İ., Baykan, U.N., Erdal, M., “Enhanced predictive models for construction costs: A case study of Turkish mass housing sector”, Computational Economics, 53(4): 3336-3344, (2019).
  3. [3] Polat, A.P., Çıracı, M., “A database model for pre-design-phase building cost estimate in Turkey”, İTÜ Journal/a, 4(2): 59-69, (2005).
  4. [4] Özmaden, M.Ş., Erdal, M., “Performance analysis of methods used in the cost estimation of residential buildings”, Konya Journal of Engineering Sciences, 8(4): 970-985, (2020).
  5. [5] Kanıt, R., Baykan, U.N., Erdal, M., “Investigation of the effects of constrained source conditions on the structure cost”, Journal of Polytechnic, 8(2): 209-221, (2005).
  6. [6] Özyürek, İ., Erdal, M., “Assessment of qualification criteria described in Public Procurement Law Code 4734 in construction works by analytic hierarchy process (AHP)”, Gazi University Journal of Science, 31(2): 437-454, (2018).
  7. [7] Yıldız, S., Kıvrak, S., Gültekin, A.B., Arslan, G., “Built environment design - social sustainability relation in urban renewal”, Sustainable Cities and Society, 60:102173, (2020).
  8. [8] Elazouni, A.M., Nosair, I.A., Mohieldin, Y.A., Mohamed, A.G., “Estimating resource requirements at conceptual design stage using neural networks”, Journal of Computing in Civil Engineering, 11: 217-223, (1997).

Details

Primary Language

English

Subjects

Engineering

Journal Section

Research Article

Publication Date

September 1, 2022

Submission Date

June 8, 2021

Acceptance Date

August 30, 2021

Published in Issue

Year 2022 Volume: 35 Number: 3

APA
Sueri, M., & Erdal, M. (2022). Early Estimation of Sewerage Line Costs with Regression Analysis. Gazi University Journal of Science, 35(3), 822-832. https://doi.org/10.35378/gujs.949726
AMA
1.Sueri M, Erdal M. Early Estimation of Sewerage Line Costs with Regression Analysis. Gazi University Journal of Science. 2022;35(3):822-832. doi:10.35378/gujs.949726
Chicago
Sueri, Murat, and Mürsel Erdal. 2022. “Early Estimation of Sewerage Line Costs With Regression Analysis”. Gazi University Journal of Science 35 (3): 822-32. https://doi.org/10.35378/gujs.949726.
EndNote
Sueri M, Erdal M (September 1, 2022) Early Estimation of Sewerage Line Costs with Regression Analysis. Gazi University Journal of Science 35 3 822–832.
IEEE
[1]M. Sueri and M. Erdal, “Early Estimation of Sewerage Line Costs with Regression Analysis”, Gazi University Journal of Science, vol. 35, no. 3, pp. 822–832, Sept. 2022, doi: 10.35378/gujs.949726.
ISNAD
Sueri, Murat - Erdal, Mürsel. “Early Estimation of Sewerage Line Costs With Regression Analysis”. Gazi University Journal of Science 35/3 (September 1, 2022): 822-832. https://doi.org/10.35378/gujs.949726.
JAMA
1.Sueri M, Erdal M. Early Estimation of Sewerage Line Costs with Regression Analysis. Gazi University Journal of Science. 2022;35:822–832.
MLA
Sueri, Murat, and Mürsel Erdal. “Early Estimation of Sewerage Line Costs With Regression Analysis”. Gazi University Journal of Science, vol. 35, no. 3, Sept. 2022, pp. 822-3, doi:10.35378/gujs.949726.
Vancouver
1.Murat Sueri, Mürsel Erdal. Early Estimation of Sewerage Line Costs with Regression Analysis. Gazi University Journal of Science. 2022 Sep. 1;35(3):822-3. doi:10.35378/gujs.949726

Cited By