ESTIMATING DISTRIBUTION PARAMETERS OF SCHEDULE ACTIVITY DURATION ON THE BASIS OF RISK RELATED TO EXPECTED PROJECT CONDITIONS

Volume: 3 Number: 1 June 1, 2011
  • Piotr Jaskowski
  • Slawomir Biruk
  • Agata Czarnigowska
EN

ESTIMATING DISTRIBUTION PARAMETERS OF SCHEDULE ACTIVITY DURATION ON THE BASIS OF RISK RELATED TO EXPECTED PROJECT CONDITIONS

Abstract

The paper focuses on handling schedule risks. For each schedule activity, a statistical distribution of its duration is to be defined. Therefore, a research was undertaken to develop a method to assist planners in determining activity duration distribution parameters according to risk level. A triangular distribution was assumed, and its parameters estimated on the basis of three input values (the most likely, pessimistic and optimistic durations). In contrast to the Program Evaluation and Review Technique, the approach proposed in the paper assumes that these input values should be evaluated independently of the particular project’s conditions and could be derived from the planner’s database of past experience. For the risk evaluation, the AHP was adopted. The proposed risk model – considering the diversity of activity types – was based on evaluating and weighting the particular project’s characteristics and expected conditions. This approach, combined with simulation technique, is argued to improve project planning and evaluation of risk mitigation alternatives

Keywords

References

  1. AbouRizk, S., Knowles, P., Hermann, U.R. (2001), “Estimating labor production rates for industrial construction activities”, Journal of Construction Engineering and Management, Vol. 127, No. 6, pp. 502-511.
  2. Chua, D.K.H., Kog, Y.C., Loh, P.K., Jaselskis, E.J. (1997), “Model for construction budget performance-neural network approach”, Journal of
  3. Construction Engineering and Management, Vol. 123, No. 33, pp. 214-222. Dawood, N. (1998), “Estimating project and activity duration: a risk management approach using network analysis”, Construction Management and Economics, Vol. 16, pp. 41-48.
  4. Dey, P.K. (2001), “Decision support system for risk management: A case study”,
  5. Management Decision, Vol. 39, No. 8, pp. 634-649. Hanna, A.S., Gunduz, M. (2005), “Early warning signs for distressed projects”,
  6. Canadian Journal of Civil Engineering, Vol. 32, No. 5, pp. 796-802. Hertz, D.B. Thomas, H. (1983), Risk analysis and its applications, John Wiley and Sons. New York, NY, USA.
  7. Jaselskis, E.J., Ashley, D.B. (1991), “Optimal allocation of project management resources for achieving success”, Journal of Construction Engineering and Management, Vol. 117, No. 2, pp. 321-340.
  8. Jaskowski, P., Biruk, S., Bucoń, R. (2010), “Assessing contractor selection criteria weights with fuzzy AHP method application in group decision environment”, Automation in Construction, Vol. 19, No. 2, pp. 120-126.

Details

Primary Language

English

Subjects

-

Journal Section

-

Authors

Piotr Jaskowski This is me

Slawomir Biruk This is me

Agata Czarnigowska This is me

Publication Date

June 1, 2011

Submission Date

June 1, 2011

Acceptance Date

-

Published in Issue

Year 2011 Volume: 3 Number: 1

APA
Jaskowski, P., Biruk, S., & Czarnigowska, A. (2011). ESTIMATING DISTRIBUTION PARAMETERS OF SCHEDULE ACTIVITY DURATION ON THE BASIS OF RISK RELATED TO EXPECTED PROJECT CONDITIONS. International Journal of Business and Management Studies, 3(1), 299-307. https://izlik.org/JA89AZ92GA
AMA
1.Jaskowski P, Biruk S, Czarnigowska A. ESTIMATING DISTRIBUTION PARAMETERS OF SCHEDULE ACTIVITY DURATION ON THE BASIS OF RISK RELATED TO EXPECTED PROJECT CONDITIONS. IJBMS. 2011;3(1):299-307. https://izlik.org/JA89AZ92GA
Chicago
Jaskowski, Piotr, Slawomir Biruk, and Agata Czarnigowska. 2011. “ESTIMATING DISTRIBUTION PARAMETERS OF SCHEDULE ACTIVITY DURATION ON THE BASIS OF RISK RELATED TO EXPECTED PROJECT CONDITIONS”. International Journal of Business and Management Studies 3 (1): 299-307. https://izlik.org/JA89AZ92GA.
EndNote
Jaskowski P, Biruk S, Czarnigowska A (June 1, 2011) ESTIMATING DISTRIBUTION PARAMETERS OF SCHEDULE ACTIVITY DURATION ON THE BASIS OF RISK RELATED TO EXPECTED PROJECT CONDITIONS. International Journal of Business and Management Studies 3 1 299–307.
IEEE
[1]P. Jaskowski, S. Biruk, and A. Czarnigowska, “ESTIMATING DISTRIBUTION PARAMETERS OF SCHEDULE ACTIVITY DURATION ON THE BASIS OF RISK RELATED TO EXPECTED PROJECT CONDITIONS”, IJBMS, vol. 3, no. 1, pp. 299–307, June 2011, [Online]. Available: https://izlik.org/JA89AZ92GA
ISNAD
Jaskowski, Piotr - Biruk, Slawomir - Czarnigowska, Agata. “ESTIMATING DISTRIBUTION PARAMETERS OF SCHEDULE ACTIVITY DURATION ON THE BASIS OF RISK RELATED TO EXPECTED PROJECT CONDITIONS”. International Journal of Business and Management Studies 3/1 (June 1, 2011): 299-307. https://izlik.org/JA89AZ92GA.
JAMA
1.Jaskowski P, Biruk S, Czarnigowska A. ESTIMATING DISTRIBUTION PARAMETERS OF SCHEDULE ACTIVITY DURATION ON THE BASIS OF RISK RELATED TO EXPECTED PROJECT CONDITIONS. IJBMS. 2011;3:299–307.
MLA
Jaskowski, Piotr, et al. “ESTIMATING DISTRIBUTION PARAMETERS OF SCHEDULE ACTIVITY DURATION ON THE BASIS OF RISK RELATED TO EXPECTED PROJECT CONDITIONS”. International Journal of Business and Management Studies, vol. 3, no. 1, June 2011, pp. 299-07, https://izlik.org/JA89AZ92GA.
Vancouver
1.Piotr Jaskowski, Slawomir Biruk, Agata Czarnigowska. ESTIMATING DISTRIBUTION PARAMETERS OF SCHEDULE ACTIVITY DURATION ON THE BASIS OF RISK RELATED TO EXPECTED PROJECT CONDITIONS. IJBMS [Internet]. 2011 Jun. 1;3(1):299-307. Available from: https://izlik.org/JA89AZ92GA