Assembly Line Balancing Problem with Stochastic Sequence-Dependent Setup Times

Volume: 21 Number: 4 August 31, 2015
EN TR

Assembly Line Balancing Problem with Stochastic Sequence-Dependent Setup Times

Abstract

There is limited number of papers which consider setup times in assembly line balancing literature. Additionally, in these studies setup times are assumed as deterministic. Nevertheless, task and setup times can include variation due to human factors, machine breakdowns, lack of equipment and environmental factors in real life applications. Therefore, in this study assembly line balancing problem with stochastic sequence-dependent setup time is studied. A mathematical model is proposed for solving the problem and computational analysis is made on certain test problems.

Keywords

References

  1. Boysen N, Fliedner M, Scholl A. “A Classification of Assembly Line Balancing Problems”. European Journal of Operational Research, 183(2), 674-693, 2007.
  2. Battaïa O, Dolgui A. “A Taxonomy of Line Balancing Problems and Their Solution Approaches”. International Journal of Production Economics, 142(2), 259-277, 2013.
  3. Scholl A, Boysen N, Fliedner M. "The Assembly Line Balancing and Scheduling Problem with Sequence- Dependent Setup Times: Problem Extension, Model Formulation and Efficient Heuristics". OR Spectrum, 35(1), 291-321, 2013.
  4. Andres C, Miralles C, Pastor R. "Balancing and Scheduling Tasks in Assembly Lines with Sequence-Dependent Setup Times". European Journal of Operational Research, 187(3), 1212-1223, 2008.
  5. Scholl A, Boysen N, Fliedner M. "The Sequence- Dependent Assembly Line Balancing Problem". OR Spectrum, 30(3), 579-609, 2008.
  6. Seyed-Alagheband SA, Ghomi SMTF, Zandieh M. "A Simulated Annealing Algorithm for Balancing the Assembly Line Type II Problem with Sequence- Dependent Setup Times Between Tasks". International Journal of Production Research, 49(3), 805-825, 2010.
  7. Hamta N, Ghomi SMTF. Hakimi-Asiabar M, Tabrizi PH. "Multi-objective Assembly Line Balancing Problem with Bounded Processing Times, Learning Effect, and Sequence-Dependent Engineering and Engineering Management (IEEM), IEEE International Conference, Singapore, 6-9 December 2011.
  8. Hamta N, Ghomi SMTF, Jolai F, Shirazi MA. "A Hybrid PSO Algorithm for a Multi-Objective Assembly Line Balancing Problem with Flexible Operation Times, Sequence- Dependent Setup Times and Learning Effect". International Journal of Production Economics, 141(1), 99-111, 2013.

Details

Primary Language

English

Subjects

-

Journal Section

-

Publication Date

August 31, 2015

Submission Date

September 1, 2015

Acceptance Date

-

Published in Issue

Year 2015 Volume: 21 Number: 4

APA
Diri, Z., Mete, S., Çil, Z., & Ağpak, K. (2015). Assembly Line Balancing Problem with Stochastic Sequence-Dependent Setup Times. Pamukkale Üniversitesi Mühendislik Bilimleri Dergisi, 21(4), 152-157. https://doi.org/10.5505/pajes.2015.93723
AMA
1.Diri Z, Mete S, Çil Z, Ağpak K. Assembly Line Balancing Problem with Stochastic Sequence-Dependent Setup Times. Pamukkale Üniversitesi Mühendislik Bilimleri Dergisi. 2015;21(4):152-157. doi:10.5505/pajes.2015.93723
Chicago
Diri, Zülal, Süleyman Mete, Zeynel Çil, and Kürşad Ağpak. 2015. “Assembly Line Balancing Problem With Stochastic Sequence-Dependent Setup Times”. Pamukkale Üniversitesi Mühendislik Bilimleri Dergisi 21 (4): 152-57. https://doi.org/10.5505/pajes.2015.93723.
EndNote
Diri Z, Mete S, Çil Z, Ağpak K (September 1, 2015) Assembly Line Balancing Problem with Stochastic Sequence-Dependent Setup Times. Pamukkale Üniversitesi Mühendislik Bilimleri Dergisi 21 4 152–157.
IEEE
[1]Z. Diri, S. Mete, Z. Çil, and K. Ağpak, “Assembly Line Balancing Problem with Stochastic Sequence-Dependent Setup Times”, Pamukkale Üniversitesi Mühendislik Bilimleri Dergisi, vol. 21, no. 4, pp. 152–157, Sept. 2015, doi: 10.5505/pajes.2015.93723.
ISNAD
Diri, Zülal - Mete, Süleyman - Çil, Zeynel - Ağpak, Kürşad. “Assembly Line Balancing Problem With Stochastic Sequence-Dependent Setup Times”. Pamukkale Üniversitesi Mühendislik Bilimleri Dergisi 21/4 (September 1, 2015): 152-157. https://doi.org/10.5505/pajes.2015.93723.
JAMA
1.Diri Z, Mete S, Çil Z, Ağpak K. Assembly Line Balancing Problem with Stochastic Sequence-Dependent Setup Times. Pamukkale Üniversitesi Mühendislik Bilimleri Dergisi. 2015;21:152–157.
MLA
Diri, Zülal, et al. “Assembly Line Balancing Problem With Stochastic Sequence-Dependent Setup Times”. Pamukkale Üniversitesi Mühendislik Bilimleri Dergisi, vol. 21, no. 4, Sept. 2015, pp. 152-7, doi:10.5505/pajes.2015.93723.
Vancouver
1.Zülal Diri, Süleyman Mete, Zeynel Çil, Kürşad Ağpak. Assembly Line Balancing Problem with Stochastic Sequence-Dependent Setup Times. Pamukkale Üniversitesi Mühendislik Bilimleri Dergisi. 2015 Sep. 1;21(4):152-7. doi:10.5505/pajes.2015.93723