IN LIMITED TIME CONSTRUCTION PROJECTS, TO FIGURE OUT THE MENPOWER COST BY CPM ANALYZING

Year 2004, Volume: 7 Issue: 2 - Volume: 7 Issue: 2, 159 - 167, 01.06.2004

Abstract

The goal of project planning is to make different planning upon different rules, to select the most rationalized one by analizing time, resource and cost analyses for each planning. In this study the cost of Ankara Aşı Serum ve İlaç Kontrol Instıtute building is evaluated with different programs and manpower cost of building has been calculated according to the normal complating time %5, %10 and %15 of the building the menpower costs figured out again. For each shortage of the time new work plans prepared, menpower costs calculated and related diagrams drown and time-cost comparision has been made

SÜRE KISITLI İNŞAAT PROJELERİNDE İŞGÜCÜ MALİYETİNİN CPM İLE ANALİZİ

Year 2004, Volume: 7 Issue: 2 - Volume: 7 Issue: 2, 159 - 167, 01.06.2004

Abstract

Proje planlamada amaç, farklı kurallara göre farklı planlamalar yapılması ve her planlamaya göre süre, kaynak ve maliyet analizleri yapılarak en rasyonel olanın seçilmesidir.Bu çalışmada Ankara Aşı Serum ve İlaç Kontrol Enstitüsü binasının maliyeti, farklı programlara ve işgücü durumuna göre incelenmiş, binanın öngörülen sürede tamamlanması durumundaki işgücü maliyetleri hesaplanmıştır. İşin tamamlanma süresinin %5, %10 ve %15 daha öne çekilmesi halindeki işgücü maliyetlerinin değişimi, araştırılmıştır. Her süre kısaltımı haline karşılık gelen iş programları düzenlenmiş; işgücü maliyetleri hesaplanarak ilgili diyagramlar çizilmiş ve süre-maliyet karşılaştırmaları yapılmıştır.

There are 0 citations in total.

Details

Other ID JA54DK35SG
Journal Section Research Article
Authors

Recep Kanıt This is me

Latif Onur Uğur This is me

Publication Date June 1, 2004
Submission Date June 1, 2004
Published in Issue Year 2004 Volume: 7 Issue: 2 - Volume: 7 Issue: 2

Cite

APA Kanıt, R., & Uğur, L. O. (2004). SÜRE KISITLI İNŞAAT PROJELERİNDE İŞGÜCÜ MALİYETİNİN CPM İLE ANALİZİ. Politeknik Dergisi, 7(2), 159-167.
AMA Kanıt R, Uğur LO. SÜRE KISITLI İNŞAAT PROJELERİNDE İŞGÜCÜ MALİYETİNİN CPM İLE ANALİZİ. Politeknik Dergisi. June 2004;7(2):159-167.
Chicago Kanıt, Recep, and Latif Onur Uğur. “SÜRE KISITLI İNŞAAT PROJELERİNDE İŞGÜCÜ MALİYETİNİN CPM İLE ANALİZİ”. Politeknik Dergisi 7, no. 2 (June 2004): 159-67.
EndNote Kanıt R, Uğur LO (June 1, 2004) SÜRE KISITLI İNŞAAT PROJELERİNDE İŞGÜCÜ MALİYETİNİN CPM İLE ANALİZİ. Politeknik Dergisi 7 2 159–167.
IEEE R. Kanıt and L. O. Uğur, “SÜRE KISITLI İNŞAAT PROJELERİNDE İŞGÜCÜ MALİYETİNİN CPM İLE ANALİZİ”, Politeknik Dergisi, vol. 7, no. 2, pp. 159–167, 2004.
ISNAD Kanıt, Recep - Uğur, Latif Onur. “SÜRE KISITLI İNŞAAT PROJELERİNDE İŞGÜCÜ MALİYETİNİN CPM İLE ANALİZİ”. Politeknik Dergisi 7/2 (June 2004), 159-167.
JAMA Kanıt R, Uğur LO. SÜRE KISITLI İNŞAAT PROJELERİNDE İŞGÜCÜ MALİYETİNİN CPM İLE ANALİZİ. Politeknik Dergisi. 2004;7:159–167.
MLA Kanıt, Recep and Latif Onur Uğur. “SÜRE KISITLI İNŞAAT PROJELERİNDE İŞGÜCÜ MALİYETİNİN CPM İLE ANALİZİ”. Politeknik Dergisi, vol. 7, no. 2, 2004, pp. 159-67.
Vancouver Kanıt R, Uğur LO. SÜRE KISITLI İNŞAAT PROJELERİNDE İŞGÜCÜ MALİYETİNİN CPM İLE ANALİZİ. Politeknik Dergisi. 2004;7(2):159-67.