Time - Cost Relationships for Superstructure Projects in Turkey

Volume: 31 Number: 2 March 1, 2020
TR EN

Time - Cost Relationships for Superstructure Projects in Turkey

Abstract

The concept of time-cost relationship in construction projects was first introduced by Bromilow. Bromilow used the data of the superstructure projects completed in Australia in the creation of the proposed time-cost model (BTC model). The aim of this study is to determine the time-cost relationship of superstructure projects in Turkey. Time and cost data of superstructure projects completed between the years of 1999-2018 was used in the study. Data was grouped primarily on the basis of the intended use of buildings (individual buildings, educational buildings, hospitals, industrial buildings and social housing), and then time-cost relationships were separately determined for each group. In addition, the effects of the parameters such as exchange rates and the number of non-working days on the time-cost relationship were investigated statistically. 

Keywords

References

  1. [1] Barrie, D. S., & Paulson, B. C., Professional construction management: including CM, design-construct, and general contracting. McGraw-Hill Science/Engineering/Math. 1992.
  2. [3] Bayram, S.. Duration prediction models for construction projects: In terms of cost or physical characteristics?. KSCE Journal of Civil Engineering, 2017, 21.6: 2049-2060.
  3. [2] Bromilow, F. J., Contract Time Performance Expectations and the Reality. Building Forum, 1, 70-80, 1969.
  4. [4] Petruseva, S., Pusic, D. C., & Pancovska, V. Z. Model for Predicting Construction Time by Using General Regression Neural Network. International Scientific Conference People, Buildings and Environment 2016 (PBE2016) 29 September – 1 October, 2016, Luhacovice, Czech Republic, 2016.
  5. [5] Bayram, S. & Al-Jibouri, S. Reference Class Forecasting Method in Predicting Construction Project Duration. Süleyman Demirel University Journal of Natural and Applied Sciences, 22 (3), pp.1132-1142, 2018
  6. [6] Ariful Haque, K.M., & Hasin, M.A.A. Genetic algorithm for project time-cost optimization in fuzzy environment. Journal of Industrial Engineering and Management, 5(2), pp.364-381, 2012.
  7. [7] Odabaşı, E., Models for Estimating Construction Duration: An Application for Selected Buildings on the METU Campus. Ankara: Ortadoğu Teknik Üniversitesi Uygulamalı Bilimler Enstitüsü, 2009.
  8. [8] Love, P. E. D., Tse, R. Y. C., & Edwards, D. J., Time-cost relationships in Australian building construction projects. Journal of Construction Engineering and Management (ASCE), Vol. 131, No. 2, pp. 187-194, 2005.

Details

Primary Language

English

Subjects

Civil Engineering

Journal Section

Research Article

Publication Date

March 1, 2020

Submission Date

September 3, 2018

Acceptance Date

March 18, 2019

Published in Issue

Year 2020 Volume: 31 Number: 2

APA
Sönmez, M., Dikmen, S., & Akbıyıklı, R. (2020). Time - Cost Relationships for Superstructure Projects in Turkey. Teknik Dergi, 31(2), 9869-9896. https://doi.org/10.18400/tekderg.456761
AMA
1.Sönmez M, Dikmen S, Akbıyıklı R. Time - Cost Relationships for Superstructure Projects in Turkey. Teknik Dergi. 2020;31(2):9869-9896. doi:10.18400/tekderg.456761
Chicago
Sönmez, Murat, S.ümit Dikmen, and Rıfat Akbıyıklı. 2020. “Time - Cost Relationships for Superstructure Projects in Turkey”. Teknik Dergi 31 (2): 9869-96. https://doi.org/10.18400/tekderg.456761.
EndNote
Sönmez M, Dikmen S, Akbıyıklı R (March 1, 2020) Time - Cost Relationships for Superstructure Projects in Turkey. Teknik Dergi 31 2 9869–9896.
IEEE
[1]M. Sönmez, S. Dikmen, and R. Akbıyıklı, “Time - Cost Relationships for Superstructure Projects in Turkey”, Teknik Dergi, vol. 31, no. 2, pp. 9869–9896, Mar. 2020, doi: 10.18400/tekderg.456761.
ISNAD
Sönmez, Murat - Dikmen, S.ümit - Akbıyıklı, Rıfat. “Time - Cost Relationships for Superstructure Projects in Turkey”. Teknik Dergi 31/2 (March 1, 2020): 9869-9896. https://doi.org/10.18400/tekderg.456761.
JAMA
1.Sönmez M, Dikmen S, Akbıyıklı R. Time - Cost Relationships for Superstructure Projects in Turkey. Teknik Dergi. 2020;31:9869–9896.
MLA
Sönmez, Murat, et al. “Time - Cost Relationships for Superstructure Projects in Turkey”. Teknik Dergi, vol. 31, no. 2, Mar. 2020, pp. 9869-96, doi:10.18400/tekderg.456761.
Vancouver
1.Murat Sönmez, S.ümit Dikmen, Rıfat Akbıyıklı. Time - Cost Relationships for Superstructure Projects in Turkey. Teknik Dergi. 2020 Mar. 1;31(2):9869-96. doi:10.18400/tekderg.456761

Cited By