Time - Cost Relationships for Superstructure Projects in Turkey
Abstract
The concept of time-cost relationship in construction projects was first introduced by Bromilow. Bromilow used the data of the superstructure projects completed in Australia in the creation of the proposed time-cost model (BTC model). The aim of this study is to determine the time-cost relationship of superstructure projects in Turkey. Time and cost data of superstructure projects completed between the years of 1999-2018 was used in the study. Data was grouped primarily on the basis of the intended use of buildings (individual buildings, educational buildings, hospitals, industrial buildings and social housing), and then time-cost relationships were separately determined for each group. In addition, the effects of the parameters such as exchange rates and the number of non-working days on the time-cost relationship were investigated statistically.
Keywords
References
- [1] Barrie, D. S., & Paulson, B. C., Professional construction management: including CM, design-construct, and general contracting. McGraw-Hill Science/Engineering/Math. 1992.
- [3] Bayram, S.. Duration prediction models for construction projects: In terms of cost or physical characteristics?. KSCE Journal of Civil Engineering, 2017, 21.6: 2049-2060.
- [2] Bromilow, F. J., Contract Time Performance Expectations and the Reality. Building Forum, 1, 70-80, 1969.
- [4] Petruseva, S., Pusic, D. C., & Pancovska, V. Z. Model for Predicting Construction Time by Using General Regression Neural Network. International Scientific Conference People, Buildings and Environment 2016 (PBE2016) 29 September – 1 October, 2016, Luhacovice, Czech Republic, 2016.
- [5] Bayram, S. & Al-Jibouri, S. Reference Class Forecasting Method in Predicting Construction Project Duration. Süleyman Demirel University Journal of Natural and Applied Sciences, 22 (3), pp.1132-1142, 2018
- [6] Ariful Haque, K.M., & Hasin, M.A.A. Genetic algorithm for project time-cost optimization in fuzzy environment. Journal of Industrial Engineering and Management, 5(2), pp.364-381, 2012.
- [7] Odabaşı, E., Models for Estimating Construction Duration: An Application for Selected Buildings on the METU Campus. Ankara: Ortadoğu Teknik Üniversitesi Uygulamalı Bilimler Enstitüsü, 2009.
- [8] Love, P. E. D., Tse, R. Y. C., & Edwards, D. J., Time-cost relationships in Australian building construction projects. Journal of Construction Engineering and Management (ASCE), Vol. 131, No. 2, pp. 187-194, 2005.
Details
Primary Language
English
Subjects
Civil Engineering
Journal Section
Research Article
Authors
Murat Sönmez
*
0000-0003-2328-6817
Türkiye
S.ümit Dikmen
This is me
0000-0002-4003-1368
Türkiye
Rıfat Akbıyıklı
0000-0003-1584-9384
Türkiye
Publication Date
March 1, 2020
Submission Date
September 3, 2018
Acceptance Date
March 18, 2019
Published in Issue
Year 2020 Volume: 31 Number: 2
Cited By
Investigation of Organizational and Regional Perceptions on the Changes in Construction Projects
Teknik Dergi
https://doi.org/10.18400/tekderg.595995Scheduling, Management and Optimization of Construction Process
Teknik Dergi
https://doi.org/10.18400/tekderg.981601Transportation project bundling policy impacts on construction time delay: some empirical evidence
Transportation Research Part A: Policy and Practice
https://doi.org/10.1016/j.tra.2025.104698A generalized artificial neural network (ANN) model for predicting construction project durations based on cost and geolocation data
Engineering, Construction and Architectural Management
https://doi.org/10.1108/ECAM-07-2025-1227