Time - Cost Relationships for Superstructure Projects in Turkey

Cilt: 31 Sayı: 2 1 Mart 2020
PDF İndir
TR EN

Time - Cost Relationships for Superstructure Projects in Turkey

Öz

The concept of time-cost relationship in construction projects was first introduced by Bromilow. Bromilow used the data of the superstructure projects completed in Australia in the creation of the proposed time-cost model (BTC model). The aim of this study is to determine the time-cost relationship of superstructure projects in Turkey. Time and cost data of superstructure projects completed between the years of 1999-2018 was used in the study. Data was grouped primarily on the basis of the intended use of buildings (individual buildings, educational buildings, hospitals, industrial buildings and social housing), and then time-cost relationships were separately determined for each group. In addition, the effects of the parameters such as exchange rates and the number of non-working days on the time-cost relationship were investigated statistically. 

Anahtar Kelimeler

Kaynakça

  1. [1] Barrie, D. S., & Paulson, B. C., Professional construction management: including CM, design-construct, and general contracting. McGraw-Hill Science/Engineering/Math. 1992.
  2. [3] Bayram, S.. Duration prediction models for construction projects: In terms of cost or physical characteristics?. KSCE Journal of Civil Engineering, 2017, 21.6: 2049-2060.
  3. [2] Bromilow, F. J., Contract Time Performance Expectations and the Reality. Building Forum, 1, 70-80, 1969.
  4. [4] Petruseva, S., Pusic, D. C., & Pancovska, V. Z. Model for Predicting Construction Time by Using General Regression Neural Network. International Scientific Conference People, Buildings and Environment 2016 (PBE2016) 29 September – 1 October, 2016, Luhacovice, Czech Republic, 2016.
  5. [5] Bayram, S. & Al-Jibouri, S. Reference Class Forecasting Method in Predicting Construction Project Duration. Süleyman Demirel University Journal of Natural and Applied Sciences, 22 (3), pp.1132-1142, 2018
  6. [6] Ariful Haque, K.M., & Hasin, M.A.A. Genetic algorithm for project time-cost optimization in fuzzy environment. Journal of Industrial Engineering and Management, 5(2), pp.364-381, 2012.
  7. [7] Odabaşı, E., Models for Estimating Construction Duration: An Application for Selected Buildings on the METU Campus. Ankara: Ortadoğu Teknik Üniversitesi Uygulamalı Bilimler Enstitüsü, 2009.
  8. [8] Love, P. E. D., Tse, R. Y. C., & Edwards, D. J., Time-cost relationships in Australian building construction projects. Journal of Construction Engineering and Management (ASCE), Vol. 131, No. 2, pp. 187-194, 2005.

Ayrıntılar

Birincil Dil

İngilizce

Konular

İnşaat Mühendisliği

Bölüm

Araştırma Makalesi

Yayımlanma Tarihi

1 Mart 2020

Gönderilme Tarihi

3 Eylül 2018

Kabul Tarihi

18 Mart 2019

Yayımlandığı Sayı

Yıl 2020 Cilt: 31 Sayı: 2

Kaynak Göster

APA
Sönmez, M., Dikmen, S., & Akbıyıklı, R. (2020). Time - Cost Relationships for Superstructure Projects in Turkey. Teknik Dergi, 31(2), 9869-9896. https://doi.org/10.18400/tekderg.456761
AMA
1.Sönmez M, Dikmen S, Akbıyıklı R. Time - Cost Relationships for Superstructure Projects in Turkey. Teknik Dergi. 2020;31(2):9869-9896. doi:10.18400/tekderg.456761
Chicago
Sönmez, Murat, S.ümit Dikmen, ve Rıfat Akbıyıklı. 2020. “Time - Cost Relationships for Superstructure Projects in Turkey”. Teknik Dergi 31 (2): 9869-96. https://doi.org/10.18400/tekderg.456761.
EndNote
Sönmez M, Dikmen S, Akbıyıklı R (01 Mart 2020) Time - Cost Relationships for Superstructure Projects in Turkey. Teknik Dergi 31 2 9869–9896.
IEEE
[1]M. Sönmez, S. Dikmen, ve R. Akbıyıklı, “Time - Cost Relationships for Superstructure Projects in Turkey”, Teknik Dergi, c. 31, sy 2, ss. 9869–9896, Mar. 2020, doi: 10.18400/tekderg.456761.
ISNAD
Sönmez, Murat - Dikmen, S.ümit - Akbıyıklı, Rıfat. “Time - Cost Relationships for Superstructure Projects in Turkey”. Teknik Dergi 31/2 (01 Mart 2020): 9869-9896. https://doi.org/10.18400/tekderg.456761.
JAMA
1.Sönmez M, Dikmen S, Akbıyıklı R. Time - Cost Relationships for Superstructure Projects in Turkey. Teknik Dergi. 2020;31:9869–9896.
MLA
Sönmez, Murat, vd. “Time - Cost Relationships for Superstructure Projects in Turkey”. Teknik Dergi, c. 31, sy 2, Mart 2020, ss. 9869-96, doi:10.18400/tekderg.456761.
Vancouver
1.Murat Sönmez, S.ümit Dikmen, Rıfat Akbıyıklı. Time - Cost Relationships for Superstructure Projects in Turkey. Teknik Dergi. 01 Mart 2020;31(2):9869-96. doi:10.18400/tekderg.456761

Cited By