Correcting Monte Carlo Bias In Tunnel Scheduling: A Comparative TD–Des Framework for Hybrid NATM–TBM Projects
Abstract
This research proposes a corrected Monte Carlo (MC) framework to examine structural bias in probabilistic tunnel scheduling. The framework integrates parallel multi-front excavation modelling, One-At-a-Time sensitivity analysis, and an outer-loop Monte Carlo correction that explicitly captures parameter-level uncertainty. Time-driven and discrete event simulation approaches are evaluated using a common dataset and validated against field data from the Eurasia Tunnel project in Istanbul. Results show strong agreement with documented tunnel boring machine performance, with advance-rate deviation below 0.4%. Parallel multi-front execution reduces the predicted P50 project duration by 64.3% and cost by 14.9% relative to a fully sequential baseline, while a combined resource-optimisation scenario (increased crew size, equipment, and efficiency) yields a further 22.8–22.9% schedule improvement that brackets the project’s documented 17.1% early completion.
Keywords
References
- Flyvbjerg, B., Holm, M.K.S. and Buhl, S.L. (2002), "Underestimating costs in public works projects: Error or lie?", Journal of the American Planning Association, Vol. 68 No. 3, pp. 279–295, doi: 10.1080/01944360208976273.
- Cantarelli, C.C., Flyvbjerg, B., Molin, E.J.E. and van Wee, B. (2010), "Cost overruns in large-scale transportation infrastructure projects: explanations and their theoretical embeddedness", European Journal of Transport and Infrastructure Research, Vol. 10 No. 1, pp. 5–18.
- Touran, A. (2010), "Probabilistic approach for budgeting in portfolio of projects", Journal of Construction Engineering and Management, ASCE, Vol. 136 No. 3, pp. 361–366, doi: 10.1061/(ASCE)CO.1943-7862.0000139.
- Flyvbjerg, B., Bruzelius, N., Rothengatter, W. (2003), “Megaprojects and Risk: An Anatomy of Ambitin”, Cambridge University Press, ISBN: 0521009464, 9780521009461
- Banks, J., Carson II, J. S., Nelson, B. L., Nicol, D. M. (2014), “Discrete-Event System Simulation”, Fifth Edition, Pearson Prentice Hall.
- Halpin, D.W. (1977), "CYCLONE — Method for modeling job site processes", Journal of the Construction Division, ASCE, Vol. 103 No. 3, pp. 489–499.
- AbouRizk, S.M. and Halpin, D.W. (1992), "Statistical properties of construction productivity", Journal of Construction Engineering and Management, ASCE, Vol. 118 No. 3, pp. 494–514, doi: 10.1061/(ASCE)0733-9364(1992)118:3(494).
- Einstein, H.H. (1996), "Risk and risk analysis in rock engineering", Tunnelling and Underground Space Technology, Vol. 11 No. 2, pp. 141–155, doi: 10.1016/0886-7798(96)00014-4.
Details
Primary Language
English
Subjects
Civil Construction Engineering, Construction Business
Journal Section
Research Article
Authors
Early Pub Date
September 28, 2026
Publication Date
-
Submission Date
April 29, 2026
Acceptance Date
September 25, 2026
Published in Issue
Year 2026 Number: Advanced Online Publication
APA
Gürcanlı, G. E., & Akboğa Kale, Ö. (2026). Correcting Monte Carlo Bias In Tunnel Scheduling: A Comparative TD–Des Framework for Hybrid NATM–TBM Projects. Turkish Journal of Civil Engineering, Advanced Online Publication. https://doi.org/10.18400/tjce.1940246
AMA
1.Gürcanlı GE, Akboğa Kale Ö. Correcting Monte Carlo Bias In Tunnel Scheduling: A Comparative TD–Des Framework for Hybrid NATM–TBM Projects. TJCE. 2026;(Advanced Online Publication). doi:10.18400/tjce.1940246
Chicago
Gürcanlı, Gürkan Emre, and Özge Akboğa Kale. 2026. “Correcting Monte Carlo Bias In Tunnel Scheduling: A Comparative TD–Des Framework for Hybrid NATM–TBM Projects”. Turkish Journal of Civil Engineering, no. Advanced Online Publication. https://doi.org/10.18400/tjce.1940246.
EndNote
Gürcanlı GE, Akboğa Kale Ö (September 1, 2026) Correcting Monte Carlo Bias In Tunnel Scheduling: A Comparative TD–Des Framework for Hybrid NATM–TBM Projects. Turkish Journal of Civil Engineering Advanced Online Publication
IEEE
[1]G. E. Gürcanlı and Ö. Akboğa Kale, “Correcting Monte Carlo Bias In Tunnel Scheduling: A Comparative TD–Des Framework for Hybrid NATM–TBM Projects”, TJCE, no. Advanced Online Publication, Sept. 2026, doi: 10.18400/tjce.1940246.
ISNAD
Gürcanlı, Gürkan Emre - Akboğa Kale, Özge. “Correcting Monte Carlo Bias In Tunnel Scheduling: A Comparative TD–Des Framework for Hybrid NATM–TBM Projects”. Turkish Journal of Civil Engineering. Advanced Online Publication (September 1, 2026). https://doi.org/10.18400/tjce.1940246.
JAMA
1.Gürcanlı GE, Akboğa Kale Ö. Correcting Monte Carlo Bias In Tunnel Scheduling: A Comparative TD–Des Framework for Hybrid NATM–TBM Projects. TJCE. 2026. doi:10.18400/tjce.1940246.
MLA
Gürcanlı, Gürkan Emre, and Özge Akboğa Kale. “Correcting Monte Carlo Bias In Tunnel Scheduling: A Comparative TD–Des Framework for Hybrid NATM–TBM Projects”. Turkish Journal of Civil Engineering, no. Advanced Online Publication, Sept. 2026, doi:10.18400/tjce.1940246.
Vancouver
1.Gürkan Emre Gürcanlı, Özge Akboğa Kale. Correcting Monte Carlo Bias In Tunnel Scheduling: A Comparative TD–Des Framework for Hybrid NATM–TBM Projects. TJCE. 2026 Sep. 1;(Advanced Online Publication). doi:10.18400/tjce.1940246