Correcting Monte Carlo Bias In Tunnel Scheduling: A Comparative TD–Des Framework for Hybrid NATM–TBM Projects

Sayı: Advanced Online Publication Erken Görünüm Tarihi: 28 Eylül 2026
PDF İndir
TR EN

Correcting Monte Carlo Bias In Tunnel Scheduling: A Comparative TD–Des Framework for Hybrid NATM–TBM Projects

Öz

This research proposes a corrected Monte Carlo (MC) framework to examine structural bias in probabilistic tunnel scheduling. The framework integrates parallel multi-front excavation modelling, One-At-a-Time sensitivity analysis, and an outer-loop Monte Carlo correction that explicitly captures parameter-level uncertainty. Time-driven and discrete event simulation approaches are evaluated using a common dataset and validated against field data from the Eurasia Tunnel project in Istanbul. Results show strong agreement with documented tunnel boring machine performance, with advance-rate deviation below 0.4%. Parallel multi-front execution reduces the predicted P50 project duration by 64.3% and cost by 14.9% relative to a fully sequential baseline, while a combined resource-optimisation scenario (increased crew size, equipment, and efficiency) yields a further 22.8–22.9% schedule improvement that brackets the project’s documented 17.1% early completion.

Anahtar Kelimeler

Kaynakça

  1. Flyvbjerg, B., Holm, M.K.S. and Buhl, S.L. (2002), "Underestimating costs in public works projects: Error or lie?", Journal of the American Planning Association, Vol. 68 No. 3, pp. 279–295, doi: 10.1080/01944360208976273.
  2. Cantarelli, C.C., Flyvbjerg, B., Molin, E.J.E. and van Wee, B. (2010), "Cost overruns in large-scale transportation infrastructure projects: explanations and their theoretical embeddedness", European Journal of Transport and Infrastructure Research, Vol. 10 No. 1, pp. 5–18.
  3. Touran, A. (2010), "Probabilistic approach for budgeting in portfolio of projects", Journal of Construction Engineering and Management, ASCE, Vol. 136 No. 3, pp. 361–366, doi: 10.1061/(ASCE)CO.1943-7862.0000139.
  4. Flyvbjerg, B., Bruzelius, N., Rothengatter, W. (2003), “Megaprojects and Risk: An Anatomy of Ambitin”, Cambridge University Press, ISBN: 0521009464, 9780521009461
  5. Banks, J., Carson II, J. S., Nelson, B. L., Nicol, D. M. (2014), “Discrete-Event System Simulation”, Fifth Edition, Pearson Prentice Hall.
  6. Halpin, D.W. (1977), "CYCLONE — Method for modeling job site processes", Journal of the Construction Division, ASCE, Vol. 103 No. 3, pp. 489–499.
  7. AbouRizk, S.M. and Halpin, D.W. (1992), "Statistical properties of construction productivity", Journal of Construction Engineering and Management, ASCE, Vol. 118 No. 3, pp. 494–514, doi: 10.1061/(ASCE)0733-9364(1992)118:3(494).
  8. Einstein, H.H. (1996), "Risk and risk analysis in rock engineering", Tunnelling and Underground Space Technology, Vol. 11 No. 2, pp. 141–155, doi: 10.1016/0886-7798(96)00014-4.

Ayrıntılar

Birincil Dil

İngilizce

Konular

İnşaat Yapım Mühendisliği, Yapı İşletmesi

Bölüm

Araştırma Makalesi

Erken Görünüm Tarihi

28 Eylül 2026

Yayımlanma Tarihi

-

Gönderilme Tarihi

29 Nisan 2026

Kabul Tarihi

25 Eylül 2026

Yayımlandığı Sayı

Yıl 2026 Sayı: Advanced Online Publication

Kaynak Göster

APA
Gürcanlı, G. E., & Akboğa Kale, Ö. (2026). Correcting Monte Carlo Bias In Tunnel Scheduling: A Comparative TD–Des Framework for Hybrid NATM–TBM Projects. Turkish Journal of Civil Engineering, Advanced Online Publication. https://doi.org/10.18400/tjce.1940246
AMA
1.Gürcanlı GE, Akboğa Kale Ö. Correcting Monte Carlo Bias In Tunnel Scheduling: A Comparative TD–Des Framework for Hybrid NATM–TBM Projects. tjce. 2026;(Advanced Online Publication). doi:10.18400/tjce.1940246
Chicago
Gürcanlı, Gürkan Emre, ve Özge Akboğa Kale. 2026. “Correcting Monte Carlo Bias In Tunnel Scheduling: A Comparative TD–Des Framework for Hybrid NATM–TBM Projects”. Turkish Journal of Civil Engineering, sy Advanced Online Publication. https://doi.org/10.18400/tjce.1940246.
EndNote
Gürcanlı GE, Akboğa Kale Ö (01 Eylül 2026) Correcting Monte Carlo Bias In Tunnel Scheduling: A Comparative TD–Des Framework for Hybrid NATM–TBM Projects. Turkish Journal of Civil Engineering Advanced Online Publication
IEEE
[1]G. E. Gürcanlı ve Ö. Akboğa Kale, “Correcting Monte Carlo Bias In Tunnel Scheduling: A Comparative TD–Des Framework for Hybrid NATM–TBM Projects”, tjce, sy Advanced Online Publication, Eyl. 2026, doi: 10.18400/tjce.1940246.
ISNAD
Gürcanlı, Gürkan Emre - Akboğa Kale, Özge. “Correcting Monte Carlo Bias In Tunnel Scheduling: A Comparative TD–Des Framework for Hybrid NATM–TBM Projects”. Turkish Journal of Civil Engineering. Advanced Online Publication (01 Eylül 2026). https://doi.org/10.18400/tjce.1940246.
JAMA
1.Gürcanlı GE, Akboğa Kale Ö. Correcting Monte Carlo Bias In Tunnel Scheduling: A Comparative TD–Des Framework for Hybrid NATM–TBM Projects. tjce. 2026. doi:10.18400/tjce.1940246.
MLA
Gürcanlı, Gürkan Emre, ve Özge Akboğa Kale. “Correcting Monte Carlo Bias In Tunnel Scheduling: A Comparative TD–Des Framework for Hybrid NATM–TBM Projects”. Turkish Journal of Civil Engineering, sy Advanced Online Publication, Eylül 2026, doi:10.18400/tjce.1940246.
Vancouver
1.Gürkan Emre Gürcanlı, Özge Akboğa Kale. Correcting Monte Carlo Bias In Tunnel Scheduling: A Comparative TD–Des Framework for Hybrid NATM–TBM Projects. tjce. 01 Eylül 2026;(Advanced Online Publication). doi:10.18400/tjce.1940246