Significantly improved dominance relation for no-wait flowshop scheduling problems with uncertain setup times
Abstract
The problem of minimizing total completion time (TCT) in an uncertain environment is a crucial problem in production engineering. Minimizing the TCT of a two-machine no-wait scheduling problem with uncertain and bounded setup times is known to be very difficult, and is very likely to have no optimal solution. Such problems are known as Non-deterministic Polynomial-time hard. Scheduling literature provides a mathematical dominance relation for the problem. In this article, a substantially more effective mathematical dominance relation is established. In fact, computational methods reveal that the average percentage improvement comparing the established one in this article to the one in the literature is $1407.80 \%$. Furthermore, statistical hypothesis testing is conducted to compare the means of the established dominance relation to that given in the literature, with p-values of (almost) $0$ for every case, meaning that the mean of the established dominance relation is substantially larger than the one given in the literature. Additionally, confidence intervals are constructed for each mean of the randomly generated cases for the proposed dominance relation to confirm the accuracy of the means.
Keywords
References
- [1] A. Allahverdi, Two-machine flowshop scheduling problem to minimize makespan with bounded setup and processing times, IJAM 8, 145-153, 2005.
- [2] A. Allahverdi, Two-machine flowshop scheduling problem to minimize total completion time with bounded setup and processing times, Int. J. Prod. Econ. 103 (1), 386-400, 2006.
- [3] A. Allahverdi, Two-machine flowshop scheduling problem to minimize maximum lateness with bounded setup and processing times, Kuwait J. Sci. Eng. 33 (2), 233-251, 2006.
- [4] A. Allahverdi, The third comprehensive survey on scheduling problems with setup times/costs, Eur. J. Oper. Res. 246 (2), 345-378, 2015.
- [5] A. Allahverdi, A survey of scheduling problems with no-wait in process, Eur. J. Oper. Res. 255 (3), 665-686, 2016.
- [6] A. Allahverdi, T. Aldowaisa and Y. Sotskov, Two-machine flowshop scheduling problem to minimize makespan or total completion time with random and bounded setup times, Int. J. Math. Math. Sci. 39, 2475-2486, 2003.
- [7] A. Allahverdi and M. Allahverdi, Two-machine no-wait flowshop scheduling problem with uncertain setup times to minimize maximum lateness, Comput. Appl. Math. 37 (5), 6774-6794, 2018.
- [8] A. Allahverdi and H. Aydilek, Heuristics for two-machine flowshop scheduling problem to minimize maximum lateness with bounded processing times, Comput. Math. with Appl. 60 (5), 1374-1384, 2010.
Details
Primary Language
English
Subjects
Statistics
Journal Section
Research Article
Authors
Publication Date
March 31, 2023
Submission Date
November 28, 2020
Acceptance Date
September 19, 2022
Published in Issue
Year 2023 Volume: 52 Number: 2
APA
Allahverdi, M. (2023). Significantly improved dominance relation for no-wait flowshop scheduling problems with uncertain setup times. Hacettepe Journal of Mathematics and Statistics, 52(2), 487-498. https://doi.org/10.15672/hujms.831074
AMA
1.Allahverdi M. Significantly improved dominance relation for no-wait flowshop scheduling problems with uncertain setup times. Hacettepe Journal of Mathematics and Statistics. 2023;52(2):487-498. doi:10.15672/hujms.831074
Chicago
Allahverdi, Muberra. 2023. “Significantly Improved Dominance Relation for No-Wait Flowshop Scheduling Problems With Uncertain Setup Times”. Hacettepe Journal of Mathematics and Statistics 52 (2): 487-98. https://doi.org/10.15672/hujms.831074.
EndNote
Allahverdi M (March 1, 2023) Significantly improved dominance relation for no-wait flowshop scheduling problems with uncertain setup times. Hacettepe Journal of Mathematics and Statistics 52 2 487–498.
IEEE
[1]M. Allahverdi, “Significantly improved dominance relation for no-wait flowshop scheduling problems with uncertain setup times”, Hacettepe Journal of Mathematics and Statistics, vol. 52, no. 2, pp. 487–498, Mar. 2023, doi: 10.15672/hujms.831074.
ISNAD
Allahverdi, Muberra. “Significantly Improved Dominance Relation for No-Wait Flowshop Scheduling Problems With Uncertain Setup Times”. Hacettepe Journal of Mathematics and Statistics 52/2 (March 1, 2023): 487-498. https://doi.org/10.15672/hujms.831074.
JAMA
1.Allahverdi M. Significantly improved dominance relation for no-wait flowshop scheduling problems with uncertain setup times. Hacettepe Journal of Mathematics and Statistics. 2023;52:487–498.
MLA
Allahverdi, Muberra. “Significantly Improved Dominance Relation for No-Wait Flowshop Scheduling Problems With Uncertain Setup Times”. Hacettepe Journal of Mathematics and Statistics, vol. 52, no. 2, Mar. 2023, pp. 487-98, doi:10.15672/hujms.831074.
Vancouver
1.Muberra Allahverdi. Significantly improved dominance relation for no-wait flowshop scheduling problems with uncertain setup times. Hacettepe Journal of Mathematics and Statistics. 2023 Mar. 1;52(2):487-98. doi:10.15672/hujms.831074
Cited By
Algorithms for three-machine flowshop scheduling problem to minimize makespan with uncertain processing times
RAIRO - Operations Research
https://doi.org/10.1051/ro/2023091The Fourth Comprehensive Review of Scheduling Problems with Setup Times
European Journal of Operational Research
https://doi.org/10.1016/j.ejor.2026.03.041