Abstract
In this paper, we considered a two-objective machine-scheduling problem under sequence-dependent setup time, release date and due date constraints. The problem is formulated as a multi-objective mixed-integer programming model. Two conflicting objectives are considered as minimization of maximum completion time (makespan) and total tardiness. Despite the most use of metaheuristics in this kind of multi-objective problems, here, we try to solve the problem by transforming the two-objectives as a single objective using scalarization techniques. Test instances are generated as proposed in the scheduling literature. The solutions are obtained using Weighted Sum Scalarization, Benson’s Method and Pascoletti−Serafini Method. In addition, a comparison of scalarization techniques using Δ performance metric is given on the considered problem instances. The obtained results are evaluated and Δ values, which were obtained for Benson’s method, are mostly better than other techniques for the generated test problems.