Production lot sizing with quality screening, rework and shortages backordered
Abstract
In the classic EOQ and EPQ models, the assumption that all products are of good quality is not always valid. In some cases, the production system may produce a certain amount of defective products due to human errors and/or wear of machinery and equipment. In the literature, defective products obtained with quality screening are categorized as scrap, reworkable, low quality, etc. Generally, low-quality products are sold at a reduced price in lots at the end of the selection procedure, while scrap products are eliminated from the inventory at a certain cost. Reworkable products are also reworked at the end of the quality control period and turned into good products. In our study, screening activities are carried out during the production period in order to acquire the perfect items to run into the demand. For the remaining products, screening activity begins at the end of the production period. Allowing backorder in production systems both provides efficient production schedules and reduces operating costs. In this study, an EPQ model was constructed in which all defective products are taken at coincidental and reworked, and shortages are allowed. Sensitivity analyzes are also provided to evaluate the effects of changes in design variables on the optimal solution and to obtain feasible conditions.
Keywords
References
- [1] Harris FW. “How many parts to make at once”. Factory: The Magazine of Management, 38(6), 947-950, 1913.
- [2] Taft E W. “The most economical production lot”. The Iron Age, 101, 1410-1412, 1918.
- [3] Salameh M, Jaber M. “Economic production quantity model for items with imperfect quality”. International Journal of Production Economics, 64, 59-64, 2000.
- [4] Hayek PA, Salameh MK. “Production lot sizing with the reworking of imperfect quality items produced”. Production Planning & Control, 12, 584-590, 2001.
- [5] Chiu YP. “Determining the optimal lot size for the finite production model with random defective rate, the rework process, and backlogging”. Engineering Optimization, 35, 427-437, 2003.
- [6] Chiu SP, Chiu YP. “An economic production quantity model with the rework process of repairable defective items”. Journal of Information and Optimization Sciences, 24, 569-582, 2003.
- [7] Chan WM, Ibrahim RN, Lochert PB. “A new EPQ model: integrating lower pricing, rework and reject situations”. Production Planning & Control, 14, 588-595, 2003.
- [8] Chiu SW, Gong DC. “Determining the optimal lot size for the finite production model with an imperfect rework process of defective items”. Journal of Information and Optimization Sciences, 25, 105-119, 2004.
Details
Primary Language
English
Subjects
Engineering
Journal Section
Research Article
Publication Date
August 31, 2022
Submission Date
February 6, 2021
Acceptance Date
November 11, 2021
Published in Issue
Year 2022 Volume: 28 Number: 4
APA
Karagül, N., & Eroğlu, A. (2022). Production lot sizing with quality screening, rework and shortages backordered. Pamukkale Üniversitesi Mühendislik Bilimleri Dergisi, 28(4), 604-612. https://izlik.org/JA23RD48NE
AMA
1.Karagül N, Eroğlu A. Production lot sizing with quality screening, rework and shortages backordered. Pamukkale Üniversitesi Mühendislik Bilimleri Dergisi. 2022;28(4):604-612. https://izlik.org/JA23RD48NE
Chicago
Karagül, Nigar, and Abdullah Eroğlu. 2022. “Production Lot Sizing With Quality Screening, Rework and Shortages Backordered”. Pamukkale Üniversitesi Mühendislik Bilimleri Dergisi 28 (4): 604-12. https://izlik.org/JA23RD48NE.
EndNote
Karagül N, Eroğlu A (August 1, 2022) Production lot sizing with quality screening, rework and shortages backordered. Pamukkale Üniversitesi Mühendislik Bilimleri Dergisi 28 4 604–612.
IEEE
[1]N. Karagül and A. Eroğlu, “Production lot sizing with quality screening, rework and shortages backordered”, Pamukkale Üniversitesi Mühendislik Bilimleri Dergisi, vol. 28, no. 4, pp. 604–612, Aug. 2022, [Online]. Available: https://izlik.org/JA23RD48NE
ISNAD
Karagül, Nigar - Eroğlu, Abdullah. “Production Lot Sizing With Quality Screening, Rework and Shortages Backordered”. Pamukkale Üniversitesi Mühendislik Bilimleri Dergisi 28/4 (August 1, 2022): 604-612. https://izlik.org/JA23RD48NE.
JAMA
1.Karagül N, Eroğlu A. Production lot sizing with quality screening, rework and shortages backordered. Pamukkale Üniversitesi Mühendislik Bilimleri Dergisi. 2022;28:604–612.
MLA
Karagül, Nigar, and Abdullah Eroğlu. “Production Lot Sizing With Quality Screening, Rework and Shortages Backordered”. Pamukkale Üniversitesi Mühendislik Bilimleri Dergisi, vol. 28, no. 4, Aug. 2022, pp. 604-12, https://izlik.org/JA23RD48NE.
Vancouver
1.Nigar Karagül, Abdullah Eroğlu. Production lot sizing with quality screening, rework and shortages backordered. Pamukkale Üniversitesi Mühendislik Bilimleri Dergisi [Internet]. 2022 Aug. 1;28(4):604-12. Available from: https://izlik.org/JA23RD48NE