EVALUATING SURROGATE MEASURES OF CONSTRUCTION PROJECT SCHEDULE ROBUSTNESS

Yıl 2011, Cilt: 3 Sayı: 2, 263 - 272, 01.12.2011

Öz

Projects are subject to various uncertainties that have negative effect on activity
durations. This is most apparent in the case of construction projects. The actual
completion time of construction projects is reported to be rarely in accordance
with initial plans. A schedule considered optimal with respect to project duration
may become infeasible due to disruptions caused by uncontrollable factors.
Deficiencies of the existing methods of project scheduling gave rise to the
worldwide search for predictive (or proactive) scheduling that is expected to
provide robust schedules (immune to disturbances), thus counteracting instability
and “nervousness” of a project plan.
The baseline schedule (execution plan prepared prior to the project execution) is
to be reliable in terms of not only the total project makespan, but also timing of
particular tasks and activities – related with resource management. The main
reason for the planner’s insisting on stable baseline schedules is the necessity of
“advance booking” of key staff or equipment (to guarantee their availability) and
keeping fixed delivery dates (as required by suppliers or subcontractors).
A stable schedule with acceptable makespan performance should minimize the
instability cost function, defined as the weighted sum of the expected absolute
deviations between the predicted start times and the value that the random
variable of start time will assume during schedule execution. Computational
burden of optimizing this direct measure of schedule robustness in a real-life
project environment is quite high. Developing surrogate quantitative measures to
provide a good estimate of schedule robustness is essential for building efficient
robust scheduling algorithms. For this reasons, the aim of this paper is to
evaluate the quality of free-slack-based measures for a benchmark project. The
new approach to increasing schedule robustness, based on buffer sizing and
allocation, is proposed and tested against the existing free-slack times relocation
approaches.

Kaynakça

  • Al-Fawzan, M.A., Haouari, M. (2005), „A bi-objective model for robust resource- constrained project scheduling”, International Journal of Production Economics, Vol. 96, No. 2, pp. 175-187.
  • Chtourou, H., Haouari, M. (2008), „A two-stage-priority-rule-based algorithm for robust resource-constrained project scheduling”, Computers & Industrial
  • Engineering, Vol. 55, No. 1, pp. 183-194. Goren, S., Sabuncuoglu, I. (2008), „Robustness and stability measures for scheduling: single machine environment”, IIE Transactions, Vol. 40, No. 1, pp. 83.
  • Hazir, Ö., Haouari, M., Erel, E. (2010), „Robust scheduling and robustness measures for the discrete time/cost tade-off problem”, European Journal of
  • Operational Research, Vol. 201, No. 2, pp. 633-643. Kobylański, P., Kuchta, D. (2007), „A note on the paper by M.A. Al-Fawzan and M. Haouari about a bi-objective problem for robust resource-constrained project scheduling”, International Journal of Production Economics, Vol. 107, No. 2, pp. 501.
  • Lambrechts, O., Demeulemeester, E. Herroelen, W. (2008), „A tabu search procedure for developing robust predictive project schedules”, International
  • Journal of Production Economics, Vol. 111, No. 2, pp. 493-508. Schatteman, D., Herroelen, W., Van de Vonder, S., Boone, A. (2008),
  • „Methodology for integrated risk management and proactive scheduling of construction projects”, Journal of Construction Engineering and Management, Vol. 134, No. 11, pp. 885-893. Van de Vonder, S., Demeulemeester, E., Leus, R., Herroelen, W. (2005), „The use buffers in project management: The trade–off between stability and makespan”,
  • International Journal of Production Economics, Vol. 97, No. 2, pp. 227–240.
Yıl 2011, Cilt: 3 Sayı: 2, 263 - 272, 01.12.2011

Öz

Kaynakça

  • Al-Fawzan, M.A., Haouari, M. (2005), „A bi-objective model for robust resource- constrained project scheduling”, International Journal of Production Economics, Vol. 96, No. 2, pp. 175-187.
  • Chtourou, H., Haouari, M. (2008), „A two-stage-priority-rule-based algorithm for robust resource-constrained project scheduling”, Computers & Industrial
  • Engineering, Vol. 55, No. 1, pp. 183-194. Goren, S., Sabuncuoglu, I. (2008), „Robustness and stability measures for scheduling: single machine environment”, IIE Transactions, Vol. 40, No. 1, pp. 83.
  • Hazir, Ö., Haouari, M., Erel, E. (2010), „Robust scheduling and robustness measures for the discrete time/cost tade-off problem”, European Journal of
  • Operational Research, Vol. 201, No. 2, pp. 633-643. Kobylański, P., Kuchta, D. (2007), „A note on the paper by M.A. Al-Fawzan and M. Haouari about a bi-objective problem for robust resource-constrained project scheduling”, International Journal of Production Economics, Vol. 107, No. 2, pp. 501.
  • Lambrechts, O., Demeulemeester, E. Herroelen, W. (2008), „A tabu search procedure for developing robust predictive project schedules”, International
  • Journal of Production Economics, Vol. 111, No. 2, pp. 493-508. Schatteman, D., Herroelen, W., Van de Vonder, S., Boone, A. (2008),
  • „Methodology for integrated risk management and proactive scheduling of construction projects”, Journal of Construction Engineering and Management, Vol. 134, No. 11, pp. 885-893. Van de Vonder, S., Demeulemeester, E., Leus, R., Herroelen, W. (2005), „The use buffers in project management: The trade–off between stability and makespan”,
  • International Journal of Production Economics, Vol. 97, No. 2, pp. 227–240.
Toplam 9 adet kaynakça vardır.

Ayrıntılar

Diğer ID JA95CU86JJ
Bölüm Makaleler
Yazarlar

Piotr Jaskowski Bu kişi benim

Slawomir Biruk Bu kişi benim

Agata Czarnigowska Bu kişi benim

Yayımlanma Tarihi 1 Aralık 2011
Yayımlandığı Sayı Yıl 2011 Cilt: 3 Sayı: 2

Kaynak Göster

APA Jaskowski, P., Biruk, S., & Czarnigowska, A. (2011). EVALUATING SURROGATE MEASURES OF CONSTRUCTION PROJECT SCHEDULE ROBUSTNESS. International Journal of Business and Management Studies, 3(2), 263-272.
AMA Jaskowski P, Biruk S, Czarnigowska A. EVALUATING SURROGATE MEASURES OF CONSTRUCTION PROJECT SCHEDULE ROBUSTNESS. IJBMS. Aralık 2011;3(2):263-272.
Chicago Jaskowski, Piotr, Slawomir Biruk, ve Agata Czarnigowska. “EVALUATING SURROGATE MEASURES OF CONSTRUCTION PROJECT SCHEDULE ROBUSTNESS”. International Journal of Business and Management Studies 3, sy. 2 (Aralık 2011): 263-72.
EndNote Jaskowski P, Biruk S, Czarnigowska A (01 Aralık 2011) EVALUATING SURROGATE MEASURES OF CONSTRUCTION PROJECT SCHEDULE ROBUSTNESS. International Journal of Business and Management Studies 3 2 263–272.
IEEE P. Jaskowski, S. Biruk, ve A. Czarnigowska, “EVALUATING SURROGATE MEASURES OF CONSTRUCTION PROJECT SCHEDULE ROBUSTNESS”, IJBMS, c. 3, sy. 2, ss. 263–272, 2011.
ISNAD Jaskowski, Piotr vd. “EVALUATING SURROGATE MEASURES OF CONSTRUCTION PROJECT SCHEDULE ROBUSTNESS”. International Journal of Business and Management Studies 3/2 (Aralık 2011), 263-272.
JAMA Jaskowski P, Biruk S, Czarnigowska A. EVALUATING SURROGATE MEASURES OF CONSTRUCTION PROJECT SCHEDULE ROBUSTNESS. IJBMS. 2011;3:263–272.
MLA Jaskowski, Piotr vd. “EVALUATING SURROGATE MEASURES OF CONSTRUCTION PROJECT SCHEDULE ROBUSTNESS”. International Journal of Business and Management Studies, c. 3, sy. 2, 2011, ss. 263-72.
Vancouver Jaskowski P, Biruk S, Czarnigowska A. EVALUATING SURROGATE MEASURES OF CONSTRUCTION PROJECT SCHEDULE ROBUSTNESS. IJBMS. 2011;3(2):263-72.