A Review on the Critical Factors Causing Delay of Delivery Time in Construction Projects

Cilt: 6 Sayı: 4 7 Mart 2021
PDF İndir
EN

A Review on the Critical Factors Causing Delay of Delivery Time in Construction Projects

Öz

Completing the construction projects as per the scheduled time is an underlined issue for the success of the projects. However, several construction projects are confronted in completing within the agreed contractual project duration. In addressing influential factors contributing to delay of delivery time in construction projects, a remarkable number of studies have been conducted and published over the past decades. However, it seems that a summary and organizing of the research development in this discipline is not popularized. Therefore, this paper aims to review the existing research trend on the factors causing delays in construction projects. The review is very useful for industry practitioners and scholars to provide comprehensive and precious sources. Also, it provides a discussion, conclusion, and future research directions.

Anahtar Kelimeler

Kaynakça

  1. S. F. Arshi and M. E. Sameh , "Significant factors causing delay in the UAE construction industry," Construction Management and Economics, vol. 24(11), pp. 1167-1176, 2006. http://dx.doi.org/10.1080/01446190600 827033.
  2. M. Khoshgoftar, A. H. Abu-Bakar and O. Osman, "Causes of Delays in Iranian Construction Projects," International Journal of Construction Management, vol 10(2), pp. 53-69., 2010.
  3. C. O. Aigbavboa, W. D. Thwala and M. J. Mukuka, "Construction Project delays in Lusaka, Zambia: Causes and Effects," Journal of Economics and Behavioral Studies, vol. 6(11), pp. 848-857, 2014.
  4. R. Vahid and S. A. Abbas , "Designing Pattern for Project Delay Analysis with Several Periods Extension of Time; Continuous and Discrete (Pr-to-Pr)," Computers & Industrial Engineering, 2020. https://doi.org/10.1016/j.cie.2020.106576.
  5. K. Aliyeh , K. Eun-Seok and K. Mohammad-Hossein , "Identifying and prioritizing delay factors in Iran’s oil construction projects," International Journal of Energy Sector Management, Emerald Publishing Limited, 2020. DOI 10.1108/IJESM-04-2020-0006.
  6. A. A. Khaled , H. H. Ayman and E. N. Gamal , "Guideline for preparing comprehensive extension of time (EoT) claim," HBRC Journal, 2014. http://dx.doi.org/10.1016/j.hbrcj.2014.01.005.
  7. M. Jamil, N. A. Mufti and S. Dar Waseem, "Analysis of Time Slippage for Construction Projects in Public Sector: Owner’s Perspective," Mehran University Research Journal of Engineering & Technology, vol. 31(4), pp. 12-16, 2012.
  8. E. Adnan, A. Jomah and K. Mohan , "Delays and cost overruns in the construction projects in the Gaza Strip," Journal of Financial Management of Property and Construction, vol. 14(2), pp. 126-151, https://doi.org/10.1108/13664380910977592, 2009.

Ayrıntılar

Birincil Dil

İngilizce

Konular

Mühendislik

Bölüm

Araştırma Makalesi

Yayımlanma Tarihi

7 Mart 2021

Gönderilme Tarihi

22 Ekim 2020

Kabul Tarihi

28 Şubat 2021

Yayımlandığı Sayı

Yıl 2020 Cilt: 6 Sayı: 4

Kaynak Göster

APA
Tafesse, S. (2021). A Review on the Critical Factors Causing Delay of Delivery Time in Construction Projects. International Journal of Engineering Technologies IJET, 6(4), 69-81. https://doi.org/10.19072/ijet.815025
AMA
1.Tafesse S. A Review on the Critical Factors Causing Delay of Delivery Time in Construction Projects. IJET. 2021;6(4):69-81. doi:10.19072/ijet.815025
Chicago
Tafesse, Shitaw. 2021. “A Review on the Critical Factors Causing Delay of Delivery Time in Construction Projects”. International Journal of Engineering Technologies IJET 6 (4): 69-81. https://doi.org/10.19072/ijet.815025.
EndNote
Tafesse S (01 Mart 2021) A Review on the Critical Factors Causing Delay of Delivery Time in Construction Projects. International Journal of Engineering Technologies IJET 6 4 69–81.
IEEE
[1]S. Tafesse, “A Review on the Critical Factors Causing Delay of Delivery Time in Construction Projects”, IJET, c. 6, sy 4, ss. 69–81, Mar. 2021, doi: 10.19072/ijet.815025.
ISNAD
Tafesse, Shitaw. “A Review on the Critical Factors Causing Delay of Delivery Time in Construction Projects”. International Journal of Engineering Technologies IJET 6/4 (01 Mart 2021): 69-81. https://doi.org/10.19072/ijet.815025.
JAMA
1.Tafesse S. A Review on the Critical Factors Causing Delay of Delivery Time in Construction Projects. IJET. 2021;6:69–81.
MLA
Tafesse, Shitaw. “A Review on the Critical Factors Causing Delay of Delivery Time in Construction Projects”. International Journal of Engineering Technologies IJET, c. 6, sy 4, Mart 2021, ss. 69-81, doi:10.19072/ijet.815025.
Vancouver
1.Shitaw Tafesse. A Review on the Critical Factors Causing Delay of Delivery Time in Construction Projects. IJET. 01 Mart 2021;6(4):69-81. doi:10.19072/ijet.815025

Cited By

ijet@gelisim.edu.tr

 Alıntı-Gayriticari-Türetilemez 4.0 Uluslararası (CC BY-NC-ND 4.0)