Dissatisfaction levels of earliness and tardiness durations by relaxing common due date on single machine scheduling problems
Abstract
This
paper investigates single machine earliness/tardiness problem considering the
decision maker’s tolerances for earliness and tardiness durations in case of a
restrictive common due date. In many classical or basic earliness/tardiness
problems, due dates are accepted as deterministic or rigid numbers. In this
paper, common due date in a single machine scheduling problem is relaxed with
lower and upper bounds and these bounds are used for illustrating the decision
maker’s tolerances or satisfaction levels by using fuzzy sets. As a
complementary set of satisfaction levels, dissatisfaction levels can be encoded
with fuzzy sets. Then, this paper uses dissatisfaction levels in order to
introduce a new objective criterion that minimizes the products of earliness
and tardiness durations with dissatisfaction levels.
Keywords
Kaynakça
- [1] O.A. Arık, M.D. Toksarı, Multi-objective fuzzy parallel machine scheduling problems under fuzzy job deterioration and learning effects, International Journal of Production Research 55, 2017, 1-18.
- [2] S.E. Jayanthi, S. Karthigeyan, S. Anusuya, Minimizing earliness and tardiness costs with fuzzy processing times and fuzzy due dates in single machine scheduling using QPSO, International Journal of Pure and Applied Mathematics,115(8), 2017, Special Issue,437-442.
- [3] S. Niroomand, A. Hadi-Vencheh, N. Mirzaei, S. Molla-Alizadeh-Zavardehi, Hybrid greedy algorithms for fuzzy tardiness/earliness minimisation in a special single machine scheduling problem: case study and generalisation, International Journal of Computer Integrated Manufacturing,29(8), 2016, 870-888.
- [4] J.C. Geng, Z. Cui, X.S. Gu, Scatter search based particle swarm optimization algorithm for earliness/tardiness flowshop scheduling with uncertainty, International Journal of Automation and Computing, 13(3), 2016, 285-295.
- [5] S. Kir and H.R. Yazgan, A sequence dependent single machine scheduling problem with fuzzy axiomatic design for the penalty costs, Computers and Industrial Engineering, 92,2016, 95-104.
- [6] J. Li, J. Zhang, A 2-Approximation algorithm for the single machine due date assignment scheduling problem in fuzzy environment to minimize the total costs, Proceedings - 2015 11th International Conference on Computational Intelligence and Security, CIS 2015, 2016.
- [7] J. Behnamian, S.M.T. Fatemi Ghomi, Multi-objective fuzzy multiprocessor flowshop scheduling, Applied Soft Computing Journal,21, 2014, 139-148.
- [8] O. Engin, M.K. Yılmaz, M.E. Baysal, A.,Solving fuzzy job shop scheduling problems with availability constraints using a scatter search method, Journal of Multiple-Valued Logic and Soft Computing,21(3-4), 2013,317-334.
Ayrıntılar
Birincil Dil
İngilizce
Konular
Matematik
Bölüm
Araştırma Makalesi
Yazarlar
Yayımlanma Tarihi
2 Ağustos 2019
Gönderilme Tarihi
22 Şubat 2019
Kabul Tarihi
28 Mayıs 2019
Yayımlandığı Sayı
Yıl 2019 Cilt: 2 Sayı: 1
APA
Arık, O. A. (2019). Dissatisfaction levels of earliness and tardiness durations by relaxing common due date on single machine scheduling problems. Journal of Multidisciplinary Modeling and Optimization, 2(1), 1-15. https://izlik.org/JA99CD53WU
AMA
1.Arık OA. Dissatisfaction levels of earliness and tardiness durations by relaxing common due date on single machine scheduling problems. jmmo. 2019;2(1):1-15. https://izlik.org/JA99CD53WU
Chicago
Arık, Oğuzhan Ahmet. 2019. “Dissatisfaction levels of earliness and tardiness durations by relaxing common due date on single machine scheduling problems”. Journal of Multidisciplinary Modeling and Optimization 2 (1): 1-15. https://izlik.org/JA99CD53WU.
EndNote
Arık OA (01 Ağustos 2019) Dissatisfaction levels of earliness and tardiness durations by relaxing common due date on single machine scheduling problems. Journal of Multidisciplinary Modeling and Optimization 2 1 1–15.
IEEE
[1]O. A. Arık, “Dissatisfaction levels of earliness and tardiness durations by relaxing common due date on single machine scheduling problems”, jmmo, c. 2, sy 1, ss. 1–15, Ağu. 2019, [çevrimiçi]. Erişim adresi: https://izlik.org/JA99CD53WU
ISNAD
Arık, Oğuzhan Ahmet. “Dissatisfaction levels of earliness and tardiness durations by relaxing common due date on single machine scheduling problems”. Journal of Multidisciplinary Modeling and Optimization 2/1 (01 Ağustos 2019): 1-15. https://izlik.org/JA99CD53WU.
JAMA
1.Arık OA. Dissatisfaction levels of earliness and tardiness durations by relaxing common due date on single machine scheduling problems. jmmo. 2019;2:1–15.
MLA
Arık, Oğuzhan Ahmet. “Dissatisfaction levels of earliness and tardiness durations by relaxing common due date on single machine scheduling problems”. Journal of Multidisciplinary Modeling and Optimization, c. 2, sy 1, Ağustos 2019, ss. 1-15, https://izlik.org/JA99CD53WU.
Vancouver
1.Oğuzhan Ahmet Arık. Dissatisfaction levels of earliness and tardiness durations by relaxing common due date on single machine scheduling problems. jmmo [Internet]. 01 Ağustos 2019;2(1):1-15. Erişim adresi: https://izlik.org/JA99CD53WU