In drilling, one of the most important points to be considered is; to maintain the same direction
in the hole from start point to the bottom. But, either due to the facts resulting from the nature of
drilling or through the other reasons; the hole deviation in drilling is always encountered. In some
cases, deviation about 30° to 40° —even more— is quite possible, and if this deflection is not determined
and the necessary measures are not taken; this may lend to make big mistakes in exploration
and ore reserve calculations. The holes started vertically but ended up almost flat and having
a bearing swung in a semi-circular cource are not very rare.
Therefore, surveying the drill holes periodically and to make the necessary corrections must be
essential in diamond drilling business.
Sondajcıhkta, Üzerinde önemle durulması gereken hususlardan biri de; kuyunun başladığı noktadan
tabana kadar aynı doğrultuda açı/masının sağlanmasuiır. Ancak, gerek sondajın tabiatından gelen
nedenlerle ve gerekse diğer faktörler sebebiyle sondaj kuyularında sapma herzaman karşılaşılan
olağan hadiselerdendir. Bazı durumlarda başlangıç doğrultusuna nazaran 30 - 40 'e kadar varan
—ve hatta geçen— bu sapmalar farkına varılmadığı veya gerekli önlemler alınmadığı taktirde, aramalar
ve rezerv hesaplarında çok büyük hataların oluşmasına sebep olurlar. Unutulmamalıdır ki;
yanhş bilgi edinmektense, hiç bilmemek çok daha iyidir. Dik olarak başladığı halde, bitiminde az
çok yatay duruma gelmiş ve kuyu boyunca bükülmüş çember yayı görünümünde olan sondaj kuyuları
rastlanılmış hadiselerdendir.
Bu yüzden, delinen kuyuların eğimlerinin periodik olarak ölçülmesi ve kuyu istikametlerinde gerekli
düzeltmelerin yapılması elmaslı sondaj işlevinin ana esaslarındandır.
Diğer ID | JA22AA99VU |
---|---|
Bölüm | Araştırma Makalesi |
Yazarlar | |
Yayımlanma Tarihi | 1 Haziran 1979 |
Gönderilme Tarihi | 1 Haziran 1979 |
Yayımlandığı Sayı | Yıl 1979 Cilt: 18 Sayı: 2 |