One of the most important ways to increase productivity in industrial manufacturing is the efficient design of assembly lines. These lines consist of workstations connected by moving belts or conveyors where products are assembled part by part to reach their final form. In today's competitive manufacturing environment, organizing the work to be performed at these stations in the most efficient way is critically important. This organization process is called the “Assembly Line Balancing Problem (ALBP)” and primarily focuses on two main objectives: minimizing the number of workstations and cycle time. However, recently, this classical approach has given way to a more comprehensive perspective. Now, the optimization of resources such as workers, machines, equipment, and energy is also included in the problem. This advanced problem is termed the “Resource-Constrained ALBP (RCALBP)”. Within the scope of this study, the “Multi-Model RCALBP (MRCALBP)” was implemented in a company manufacturing industrial kitchen machines. Based on a known mathematical model in the RCALBP literature, a solution has been developed adapted to the specific needs of the company. Successful results were achieved through optimization work using 19 different resources for four different products. Two separate production lines were merged into one line, total number of resources was reduced from 46 to 31, and the number of workers was decreased from 4 to 2. At least 49% improvement in total costs has been achieved for each product. This study demonstrates that theoretical models can be successfully applied in real life and provide tangible benefits.

Keywords

Assembly Line Balancing , Industrial Case Study , Multi-Model Products , Resource-Constrained

Kaynakça

  1. Ağpak, K., & Gökçen, H. (2005). Assembly line balancing: Two resource constrained cases. International Journal Production Economics, 96, 129-140. doi: https://doi.org/10.1016/j.ijpe.2004.03.008
  2. Alakaş, H. M., Pınarbaşı, M., & Yüzükırmızı, M. (2020). Constraint programming model for resource-constrained assembly line balancing problem. Soft Computing, 24, 5367-5375. doi: https://doi.org/10.1007/s00500-019-04294-8
  3. Alakaş, H. M. (2021). General resource-constrained assembly line balancing problem: conjunction normal form based constraint programming models. Soft Computing, 25, 6101-6111. doi: https://doi.org/10.1007/s00500-021-05602-x
  4. Alakaş, H. M., & Pınarbaşı, M. (2023). Balancing of cost-oriented U-type general resource-constrained assembly line: New constraint programming models. Soft Computing, 27, 18667–18680. doi: https://doi.org/10.1007/s00500-023-09105-9
  5. Alpay, Ş. (2008). Tam zamanlı montaj hatlarında çok amaçlı karışık model sıralama için rota birleştirmeli açgözlü rassallaştırılmış uyarlamalı arama yordamı. Eskişehir Osmangazi Üniversitesi Mühendislik ve Mimarlık Fakültesi Dergisi, 21(1), 153-170.
  6. Atasagun, Y., & Kara, Y. (2014). Bacterial foraging optimization algorithm for assembly line balancing. Neural Computing and Applications, 25, 237-250. doi: https://doi.org/10.1007/s00521-013-1477-9
  7. Atasagun, Y. (2016). Tam zamanında üretim ortamlarında çok sayıda u-tipi hattın bütünleşik dengelenmesi için yeni modeller ve çözüm yaklaşımları (Doktora Tezi). Selçuk Üniversitesi Fen Bilimleri Enstitüsü, Konya.
  8. Barutçuoğlu, Ş., & Azizoğlu, M. (2011). Flexible assembly line design problem with fixed number of workstations. International Journal of Production Research, 49, 3691-3714. doi: https://doi.org/10.1080/00207543.2010.492410
  9. Baskak, M. (1998). Çok modelli/ürünlü montaj hatların dengelenmesi için yeni bir model ve çözüm yöntemi (Doktora Tezi). İstanbul Teknik Üniversitesi Fen Bilimleri Enstitüsü, İstanbul.
  10. Battaïa, O., & Dolgui, A. (2013). A taxonomy of line balancing problems and their solution approaches. International Journal of Production Economics, 142(2), 259-277. doi: https://doi.org/10.1016/j.ijpe.2012.10.020

Kaynak Göster

APA
Ceylan, M., & Hezer, S. (2025). RESOURCE-CONSTRAINED ASSEMBLY LINE BALANCING PROBLEM AND AN APPLICATION IN AN ASSEMBLY LINE. Eskişehir Osmangazi Üniversitesi Mühendislik ve Mimarlık Fakültesi Dergisi, 33(2), 1819-1831. https://doi.org/10.31796/ogummf.1607331
AMA
1.Ceylan M, Hezer S. RESOURCE-CONSTRAINED ASSEMBLY LINE BALANCING PROBLEM AND AN APPLICATION IN AN ASSEMBLY LINE. ESOGÜ Müh Mim Fak Derg. 2025;33(2):1819-1831. doi:10.31796/ogummf.1607331
Chicago
Ceylan, Mehmet, ve Seda Hezer. 2025. “RESOURCE-CONSTRAINED ASSEMBLY LINE BALANCING PROBLEM AND AN APPLICATION IN AN ASSEMBLY LINE”. Eskişehir Osmangazi Üniversitesi Mühendislik ve Mimarlık Fakültesi Dergisi 33 (2): 1819-31. https://doi.org/10.31796/ogummf.1607331.
EndNote
Ceylan M, Hezer S (01 Ağustos 2025) RESOURCE-CONSTRAINED ASSEMBLY LINE BALANCING PROBLEM AND AN APPLICATION IN AN ASSEMBLY LINE. Eskişehir Osmangazi Üniversitesi Mühendislik ve Mimarlık Fakültesi Dergisi 33 2 1819–1831.
IEEE
[1]M. Ceylan ve S. Hezer, “RESOURCE-CONSTRAINED ASSEMBLY LINE BALANCING PROBLEM AND AN APPLICATION IN AN ASSEMBLY LINE”, ESOGÜ Müh Mim Fak Derg, c. 33, sy 2, ss. 1819–1831, Ağu. 2025, doi: 10.31796/ogummf.1607331.
ISNAD
Ceylan, Mehmet - Hezer, Seda. “RESOURCE-CONSTRAINED ASSEMBLY LINE BALANCING PROBLEM AND AN APPLICATION IN AN ASSEMBLY LINE”. Eskişehir Osmangazi Üniversitesi Mühendislik ve Mimarlık Fakültesi Dergisi 33/2 (01 Ağustos 2025): 1819-1831. https://doi.org/10.31796/ogummf.1607331.
JAMA
1.Ceylan M, Hezer S. RESOURCE-CONSTRAINED ASSEMBLY LINE BALANCING PROBLEM AND AN APPLICATION IN AN ASSEMBLY LINE. ESOGÜ Müh Mim Fak Derg. 2025;33:1819–1831.
MLA
Ceylan, Mehmet, ve Seda Hezer. “RESOURCE-CONSTRAINED ASSEMBLY LINE BALANCING PROBLEM AND AN APPLICATION IN AN ASSEMBLY LINE”. Eskişehir Osmangazi Üniversitesi Mühendislik ve Mimarlık Fakültesi Dergisi, c. 33, sy 2, Ağustos 2025, ss. 1819-31, doi:10.31796/ogummf.1607331.
Vancouver
1.Mehmet Ceylan, Seda Hezer. RESOURCE-CONSTRAINED ASSEMBLY LINE BALANCING PROBLEM AND AN APPLICATION IN AN ASSEMBLY LINE. ESOGÜ Müh Mim Fak Derg. 01 Ağustos 2025;33(2):1819-31. doi:10.31796/ogummf.1607331