An interval programming based approach for fully uncertain resource-constrained project scheduling problem considering project manager’s attitude toward risk
Öz
In
recent years, there has been a growing attention to model and solve
resource-constrained project scheduling problem (RCPSP) under uncertain
environments. In most of the real-life cases, project managers may face with
many uncertainties in activity durations, resource availabilities, resource
requirements of the activities, the earliest and latest finishing times of the
activities etc. In addition to these input parameters, project schedule which
represents the starting and/or completion times of the activities should also
be considered as uncertain variables in such a fully uncertain environments
where all of the project data are imprecise. Based on this motivation, this
paper presents an interval programming based transformation approach to
overcome fully uncertain nature of the problem. In detail, classical
discrete-time binary integer programming model of the deterministic problem was
extended by incorporating interval-valued parameters and decision variables.
Then, fully uncertain RCPSP was transformed into the crisp equivalent form by
making use of interval programming, interval ranking and interval arithmetic
operations. In the proposed approach, interval arithmetic operations are
performed by using supplementary information obtained from the project manager.
Thus, the proposed approach is also able to take into account the project
managers’ attitude toward risk and produces more acceptable and risk-free
solutions. Finally, a real-life liquefied natural gas (LNG) storage tank
construction project in a petroleum refinery is presented for testing its
validity and practicality. The computational results have shown that more
applicable and information efficient project schedules can be derived via the
proposed approach according to the project manager’s attitude toward risk.
Anahtar Kelimeler
Kaynakça
- Chen Z, Demeulemeester E, Bai S, Guo Y. “Efficient priority rules for the stochastic resource-constrained project scheduling problem”. European Journal of Operational Research, 270(3), 957-967, 2018.
- Rostami S, Creemers S, Leus R. “New strategies for stochastic resource-constrained project scheduling”. Journal of Scheduling, 21(3), 349-365, 2018.
- Atli O, Kahraman C. “Fuzzy resource-constrained project scheduling using taboo search algorithm”. International Journal of Intelligent Systems, 27(10), 873-907, 2012.
- Atli O, Kahraman C. “Resource-constrained project scheduling problem with multiple execution modes and fuzzy/crisp activity durations”. Journal of Intelligent & Fuzzy Systems, 26(4), 2001-2020, 2014.
- Kahraman C, Kerre EE, Bozbura FT. Uncertainty modelling and in knowledge engineering and decision making. Proceedings of the 10th International FLINS Conference, Istanbul, Turkey, 26-29 August 2012.
- Subulan K. “Fully uncertain resource constrained project scheduling problem via interval programming: a real-life application in a LNG storage tank construction”. 2nd International Conference on Economics Business Management and Social Sciences, Belgrade, Serbia, 10-14 May 2017.
- Baykasoğlu A, Subulan K. “Constrained fuzzy arithmetic approach to fuzzy transportation problems with fuzzy decision variables”. Expert Systems with Applications, 81, 193-222, 2017.
- Baykasoğlu A, Subulan K. “A direct solution approach based on constrained fuzzy arithmetic and metaheuristic for fuzzy transportation problems”. Soft Computing, https://doi.org/10.1007/s00500-017-2890-2.
Ayrıntılar
Birincil Dil
İngilizce
Konular
Mühendislik
Bölüm
Araştırma Makalesi
Yazarlar
Yayımlanma Tarihi
28 Ağustos 2019
Gönderilme Tarihi
9 Ağustos 2018
Kabul Tarihi
-
Yayımlandığı Sayı
Yıl 2019 Cilt: 25 Sayı: 4