Causal Relationships of Readability Risks in Construction Contracts
Öz
Issues related to readability risks in contracts could exacerbate conflict, claim and dispute occurrences in construction projects. Determination of root causes of readability risks by defining casual relationships in construction contracts is essential to improve contract documentation and enable successful risk management. This paper aims to differentiate net causes from net effect factors of readability risks in construction contracts. Most significant readability risks in construction contracts were analyzed using fuzzy decision-making trial and evaluation laboratory (DEMATEL) method, which is known for its wide implementation in similar problems. Root cause degree (RCD) diagram was drawn to illustrate the differentiation of these factors by adopting maximum mean de-entropy (MMDE) algorithm. Analysis results indicated that poor grammar use, legal terminology, visual representation, and negative language were the major underlying cause factors; while lengthy document, use of abbreviations, scope complexity, controversial uses, repetitions, and ambiguous words were the net effect factors. The results are expected to improve readability of contract documents, which would contribute to more effective risk management and better allocation of project resources.
Anahtar Kelimeler
Destekleyen Kurum
The Coordinatorship of Scientific Research Projects of the Yildiz Technical University
Proje Numarası
FBA-2020-3934
Kaynakça
- Chong, H. Y. and Zin, R. M., A case study into the language structure of construction standard form in Malaysia, International Journal of Project Management 28, 601–608 2010.
- Besaiso, H., Fenn, P., Emsley, M., and Wright, D., A comparison of the suitability of FIDIC and NEC conditions of contract in Palestine: A perspective from the industry, Engineering, Construction and Architectural Management 25, 241–256 2018.
- El-Sayegh, S. M. and Mansour, M. H., Risk assessment and allocation in highway construction projects in the UAE, Journal of Management in Engineering 31, 04015004 2015.
- Zhang, L., Fenn, P., and Fu, Y., To insist or to concede? Contractors’ behavioural strategies when handling disputed claims, Engineering, Construction and Architectural Management 26, 424–443 2019.
- Cheung, S. O. and Yiu, T. W., Are construction disputes inevitable?, IEEE Transactions on Engineering Management 53, 456–470 2006.
- Saseendran, A., Bigelow, B. F., Rybkowski, Z. K., and Jourdan, D. E., Disputes in Construction : Evaluation of Contractual Effects of ConsensusDOCS, Journal of Legal Affairs and Dispute Resolution in Engineering and Construction 12, 04520008 2020.
- El-Adaway, I. H., Abotaleb, I. S., Eid, M. S., May, S., Netherton, L., and Vest, J., Contract Administration Guidelines for Public Infrastructure Projects in the United States and Saudi Arabia: Comparative Analysis Approach, Journal of Construction Engineering and Management 144, 04018031 2018.
- Love, P. E. D., Davis, P. R., Cheung, S. O., and Irani, Z., Causal discovery and inference of project disputes, IEEE Transactions on Engineering Management 58, 400–411 2011.
Ayrıntılar
Birincil Dil
İngilizce
Konular
Mühendislik
Bölüm
Araştırma Makalesi
Yayımlanma Tarihi
1 Mart 2022
Gönderilme Tarihi
6 Temmuz 2021
Kabul Tarihi
29 Kasım 2021
Yayımlandığı Sayı
Yıl 2022 Cilt: 33 Sayı: 2
APA
Koc, K., & Gurgun, A. P. (2022). Causal Relationships of Readability Risks in Construction Contracts. Teknik Dergi, 33(2), 11823-11846. https://doi.org/10.18400/tekderg.962928
AMA
1.Koc K, Gurgun AP. Causal Relationships of Readability Risks in Construction Contracts. Teknik Dergi. 2022;33(2):11823-11846. doi:10.18400/tekderg.962928
Chicago
Koc, Kerim, ve Asli Pelin Gurgun. 2022. “Causal Relationships of Readability Risks in Construction Contracts”. Teknik Dergi 33 (2): 11823-46. https://doi.org/10.18400/tekderg.962928.
EndNote
Koc K, Gurgun AP (01 Mart 2022) Causal Relationships of Readability Risks in Construction Contracts. Teknik Dergi 33 2 11823–11846.
IEEE
[1]K. Koc ve A. P. Gurgun, “Causal Relationships of Readability Risks in Construction Contracts”, Teknik Dergi, c. 33, sy 2, ss. 11823–11846, Mar. 2022, doi: 10.18400/tekderg.962928.
ISNAD
Koc, Kerim - Gurgun, Asli Pelin. “Causal Relationships of Readability Risks in Construction Contracts”. Teknik Dergi 33/2 (01 Mart 2022): 11823-11846. https://doi.org/10.18400/tekderg.962928.
JAMA
1.Koc K, Gurgun AP. Causal Relationships of Readability Risks in Construction Contracts. Teknik Dergi. 2022;33:11823–11846.
MLA
Koc, Kerim, ve Asli Pelin Gurgun. “Causal Relationships of Readability Risks in Construction Contracts”. Teknik Dergi, c. 33, sy 2, Mart 2022, ss. 11823-46, doi:10.18400/tekderg.962928.
Vancouver
1.Kerim Koc, Asli Pelin Gurgun. Causal Relationships of Readability Risks in Construction Contracts. Teknik Dergi. 01 Mart 2022;33(2):11823-46. doi:10.18400/tekderg.962928
Cited By
Scheduling, Management and Optimization of Construction Process
Teknik Dergi
https://doi.org/10.18400/tekderg.981601Technology-Enhanced Communication and Contract Management in Construction Projects
International Journal of Construction Education and Research
https://doi.org/10.1080/15578771.2025.2488912Early Prediction of Construction Disputes: Decision Support Systems with Machine Learning Techniques
Turkish Journal of Civil Engineering
https://doi.org/10.18400/tjce.1618975Harmonization of Electricity Construction Claim Prevention Mechanisms: Integration of Pre-Construction Documents, FIDIC Standards, and Standing Dispute Boards
SIGn Journal of Social Science
https://doi.org/10.37276/sjss.v6i2.562Proactive prevention of cost disputes in Chinese construction: integrating text mining and social network analysis
International Journal of Construction Management
https://doi.org/10.1080/15623599.2026.2636730