Optimization of Project Scheduling Activities in Dynamic CPM and PERT Networks Using Genetic Algorithms

Volume: 22 Number: 2 August 15, 2018

Optimization of Project Scheduling Activities in Dynamic CPM and PERT Networks Using Genetic Algorithms

Abstract

Projects consist of interconnected dimensions such as objective, time, resource and environment. Use of these dimensions in a controlled way and their effective scheduling brings the project success. Project scheduling process includes defining project activities, and estimation of time and resources to be used for the activities. At this point, the project resource-scheduling problems have begun to attract more attention after Program Evaluation and Review Technique (PERT) and Critical Path Method (CPM) are developed one after the other. However, complexity and difficulty of CPM and PERT processes led to the use of these techniques through artificial intelligence methods such as Genetic Algorithm (GA). In this study, an algorithm was proposed and developed, which determines critical path, critical activities and project completion duration by using GA, instead of CPM and PERT techniques used for network analysis within the scope of project management. The purpose of using GA was that these algorithms are an effective method for solution of complex optimization problems. Therefore, correct decisions can be made for implemented project activities by using obtained results. Thus, optimum results were obtained in a shorter time than the CPM and PERT techniques by using the model based on the dynamic algorithm. It is expected that this study will contribute to the performance field (time, speed, low error etc.) of other studies.

Keywords

References

  1. [1] Yildiz, S. 2001. Resource Leveling and Earned Value Analysis in Project Management: an Application in Construction Sector, Master Thesis, Baskent University Institute of Social Sciences, Ankara, 7-37.
  2. [2] Sivri, G. 2001. Monitoring and controlling progress in construction projects and an application for project information management system, Master Thesis, Istanbul Technical University Institute of Social Sciences, Istanbul, 1-48.
  3. [3] Kutlu, N. T. 2001. Project planning techniques and a study on application of PERT technique in construction sector, Dokuz Eylul University Journal of Social Sciences Institute, Izmir, 3 (2): 164-207.
  4. [4] Duncan, W. R. 1996. A Guide to the Project Management Body of Knowledge, Project Management Institute, USA, 3-27.
  5. [5] Ozdemir, G. 2006. The genetic algorithm methods used in resource constrained project scheduling problems and their comparison, Master Thesis, Ankara University Institute of Social Sciences.
  6. [6] Hoscan, Y. 1988. Package programs developed for CPM/PERT methods and solution used to check the project, Anadolu University, Eskisehir.
  7. [7] Leu, S. S., & Yang, C. H. 1999. A genetic-algorithm-based resource-constrained construction scheduling system. Construction Management & Economics, 17(6), 767-776.
  8. [8] Deb, K. 2001. Multi-objective optimization using evolutionary algorithms (Vol. 16). John Wiley & Sons.

Details

Primary Language

Turkish

Subjects

-

Journal Section

-

Authors

M. Ali Akcayol This is me

Publication Date

August 15, 2018

Submission Date

February 12, 2018

Acceptance Date

-

Published in Issue

Year 2018 Volume: 22 Number: 2

APA
Calp, M. H., & Akcayol, M. A. (2018). Optimization of Project Scheduling Activities in Dynamic CPM and PERT Networks Using Genetic Algorithms. Süleyman Demirel Üniversitesi Fen Bilimleri Enstitüsü Dergisi, 22(2), 615-627. https://izlik.org/JA98DJ46FK
AMA
1.Calp MH, Akcayol MA. Optimization of Project Scheduling Activities in Dynamic CPM and PERT Networks Using Genetic Algorithms. J. Nat. Appl. Sci. 2018;22(2):615-627. https://izlik.org/JA98DJ46FK
Chicago
Calp, M. Hanefi, and M. Ali Akcayol. 2018. “Optimization of Project Scheduling Activities in Dynamic CPM and PERT Networks Using Genetic Algorithms”. Süleyman Demirel Üniversitesi Fen Bilimleri Enstitüsü Dergisi 22 (2): 615-27. https://izlik.org/JA98DJ46FK.
EndNote
Calp MH, Akcayol MA (August 1, 2018) Optimization of Project Scheduling Activities in Dynamic CPM and PERT Networks Using Genetic Algorithms. Süleyman Demirel Üniversitesi Fen Bilimleri Enstitüsü Dergisi 22 2 615–627.
IEEE
[1]M. H. Calp and M. A. Akcayol, “Optimization of Project Scheduling Activities in Dynamic CPM and PERT Networks Using Genetic Algorithms”, J. Nat. Appl. Sci., vol. 22, no. 2, pp. 615–627, Aug. 2018, [Online]. Available: https://izlik.org/JA98DJ46FK
ISNAD
Calp, M. Hanefi - Akcayol, M. Ali. “Optimization of Project Scheduling Activities in Dynamic CPM and PERT Networks Using Genetic Algorithms”. Süleyman Demirel Üniversitesi Fen Bilimleri Enstitüsü Dergisi 22/2 (August 1, 2018): 615-627. https://izlik.org/JA98DJ46FK.
JAMA
1.Calp MH, Akcayol MA. Optimization of Project Scheduling Activities in Dynamic CPM and PERT Networks Using Genetic Algorithms. J. Nat. Appl. Sci. 2018;22:615–627.
MLA
Calp, M. Hanefi, and M. Ali Akcayol. “Optimization of Project Scheduling Activities in Dynamic CPM and PERT Networks Using Genetic Algorithms”. Süleyman Demirel Üniversitesi Fen Bilimleri Enstitüsü Dergisi, vol. 22, no. 2, Aug. 2018, pp. 615-27, https://izlik.org/JA98DJ46FK.
Vancouver
1.M. Hanefi Calp, M. Ali Akcayol. Optimization of Project Scheduling Activities in Dynamic CPM and PERT Networks Using Genetic Algorithms. J. Nat. Appl. Sci. [Internet]. 2018 Aug. 1;22(2):615-27. Available from: https://izlik.org/JA98DJ46FK

e-ISSN :1308-6529
Linking ISSN (ISSN-L): 1300-7688

All published articles in the journal can be accessed free of charge and are open access under the Creative Commons CC BY-NC (Attribution-NonCommercial) license. All authors and other journal users are deemed to have accepted this situation. Click here to access detailed information about the CC BY-NC license.