A Tabu Search Algorithm for an Excavator Scheduling Problem
Öz
Global sector prompts the construction firms to give a priority to time and cost factors. Thus, scheduling of the jobs is focal important to achieve cost and time objectives. Scheduling problems have gained a great importance in recent years in the construction sector. We have examined a single machine scheduling problem for an excavator used in the construction sector. There are some jobs in which each job has a normal processing time, a due date, earliness penalty and tardiness penalty. This paper presents a meta-heuristic optimization algorithm named Tabu Search (TS) to minimize the total cost and provides how it can be used to solve a wide variety of single machine scheduling problems. Computational results demonstrates that the proposed approach is a good tool for these problems.
Anahtar Kelimeler
Kaynakça
- [1] M. Ben-daya and M. Al-Fawzan, “An efficient Tabu search algorithm for the single machine mean tardiness problem”. Production Planning and Control, vol. 8, no, 7, 1997.
- [2] K. Xu, Z. Feng, and K. Jun, “A tabu-search algorithm for scheduling jobs with controllable processing times on a single machine to meet due-dates”, Computers & Operations Research, vol. 37, no. 11, pp. 1924–1938, 2010.
- [3] V. Ateş, and N. Barışçı, “Short-term load forecasting model using flower pollination algorithm”, International Scientific and Vocational Studies Journal, vol. 1, no. 1, pp. 22-29.2017.
- [4] İ. B. Koç, A. Al Janadi, and V. Ateş, “Interlock optimization of an accelerator using genetic algorithm”, International Scientific and Vocational Studies Journal, vol. 1, no. 1, pp. 30-41, 2017.
- [5] C. Oguz, F. Salman, and Z. Yalçın, “Order acceptance and scheduling decisions in make-to-order systems”, International Journal of Production Economics, vol. 125, pp. 200–211, 2010.
- [6] M. Laguna, J. W. Barnes, and F. Glover, “Tabu search methods for a single machine scheduling problem”, Journal of Intelligent Manufacturing, vol. 2, pp. 63–74, 1991.
- [7] J. S. Chen, “Using integer programming to solve the machine scheduling problem with a flexible maintenance activity”, Journal of Statistics and Management Systems, vol. 9, no. 1, pp. 87–104, 2006.
- [8] J. S. Chen, “Optimization models for the machine scheduling problem with a single flexible maintenance activity”, Engineering Optimization, vol. 38, no. 1, 53–71, 2006.
Ayrıntılar
Birincil Dil
İngilizce
Konular
Endüstri Mühendisliği
Bölüm
Araştırma Makalesi
Yayımlanma Tarihi
30 Haziran 2020
Gönderilme Tarihi
15 Nisan 2019
Kabul Tarihi
26 Mart 2020
Yayımlandığı Sayı
Yıl 2020 Cilt: 4 Sayı: 1