Cost and Time Management Efficiency Assessment for Large Road Projects Using Data Envelopment Analysis
Öz
Upon the completion of national road projects, their cost and time deviations are often reported. These deviations from the projected values are a result of complications in the time and cost management of such projects. Controlling the cost and time overrun of projects is important for successful implementation and efficient project management. However, few studies have attempted to measure the project cost and time management efficiency in civil engineering. Thus, this issue requires further investigation. In this study, large road projects that had poor cost and time management were selected. The chosen projects were configured as Decision Making Units (DMUs) in a Data Envelopment Analysis (DEA). DEA is a non-parametric modern mathematical tool for measuring relative managerial performance and determining efficient DMUs. A list containing the causes of cost and time deviations and the percentage deviation for each DMU was prepared. The cost and time management efficiency of the DMUs was calculated using DEA, and the resulting values were ordered according to importance. It is believed that this process will contribute to better cost and time management.
Anahtar Kelimeler
Kaynakça
- Ahbab, C. & Celik, T., 2012. An investigation on delay, cost overrun, quality, and health and safety problems in construction projects. Ankara, Middle East Technical University, pp. 1-6.
- Ahsan, K. & Gunawan, I., 2010. Analysis of cost and schedule performance of international development projects. International Journal of Project Management, pp. 68-78.
- Arditi, D., Akan, G. T. & Gurdamar, S., 1985. Cost overruns in public projects. International Journal of Project Management, pp. 218-224.
- Assaf, S. A. & Al-Hejji, S., 2006. Causes of delay in large construction projects. International Journal of Project Management, pp. 349-357.
- Banker, R. D., Charnes, A. & Cooper, W. W., 1984. Some Models for Estimating Technical and Scale Inefficiencies in Data Envelopment Analysis. Management Science, pp. 1078-1092.
- Besner, C. & Hobbs, B., 2006. The Perceived Vaeue And Potentiae Contribution Oe Project Manacement Practices To Project Success. Project Management Journal, pp. 37-48.
- Charnes, A., Cooper, W. W. & Rhodes, E., 1978. Measuring the efficiency of decision making units. European Journal of Operational Research, pp. 429-444.
- Cheng, Y.-M., 2014. An exploration into cost-influencing factors on construction projects. International Journal of Project Management, pp. 850-860.
Ayrıntılar
Birincil Dil
İngilizce
Konular
Mühendislik, İnşaat Mühendisliği
Bölüm
Araştırma Makalesi
Yazarlar
Changiz Ahbab
*
DOĞU AKDENİZ ÜNİVERSİTESİ
0000-0002-0780-1375
Türkiye
Sahand Daneshvar
Bu kişi benim
DOĞU AKDENİZ ÜNİVERSİTESİ
0000-0002-8597-3463
Türkiye
Tahir Celık
Bu kişi benim
ULUSLARARASI KIBRIS ÜNİVERSİTESİ
0000-0002-2943-0640
Türkiye
Yayımlanma Tarihi
1 Mart 2019
Gönderilme Tarihi
8 Ocak 2018
Kabul Tarihi
12 Kasım 2018
Yayımlandığı Sayı
Yıl 2019 Cilt: 30 Sayı: 2
Cited By
Investigation of Organizational and Regional Perceptions on the Changes in Construction Projects
Teknik Dergi
https://doi.org/10.18400/tekderg.595995Factors Affecting Productivity of Technical Personnel in Turkish Construction Industry: A Field Study
Arabian Journal for Science and Engineering
https://doi.org/10.1007/s13369-021-05789-zCost Overrun Causative Factors in Road Infrastructure Projects: A Frequency and Importance Analysis
Applied Sciences
https://doi.org/10.3390/app10165506Influence of Sector, Budget Size and Financing on Time and Cost Management of Czech International Development Projects
SHS Web of Conferences
https://doi.org/10.1051/shsconf/20219206006Kaynak Dengeleme Probleminin Arama Uzayını Paralel Programlama ile Tarayarak Kesin Çözümü
Teknik Dergi
https://doi.org/10.18400/tekderg.595238Scheduling, Management and Optimization of Construction Process
Teknik Dergi
https://doi.org/10.18400/tekderg.981601A Second Chance for Failed Projects Using Data Envelopment Analysis Based on Project Attractiveness Factors
Mathematics
https://doi.org/10.3390/math12233761Prediction of the project schedule performance outcome with last planner system and social network analysis indicators
Engineering, Construction and Architectural Management
https://doi.org/10.1108/ECAM-03-2025-0424